Try an ExternalTaskSensor

Thanks,

Scott

On Jun 2, 2017, 3:28 AM -0700, Zsolt Tóth <[email protected]>, wrote:
> Hi,
>
> is there a way to execute all tasks of a dag without interruption? Right
> now the scheduler jumps between dags, and eventually they will all finish.
> What I want is to force the scheduler to finish a dag completely, and jump
> to the next one afterwards.
> I think I could set all tasks of the dag to the same priority, giving each
> dag a different prio this way, but then I'll also have a precedence between
> DAGs, which I don't want.
>
> Thanks,
> Zsolt