Hi Scott,

thanks for the answer. However, I absolutely don't want to make one Dag
dependent of the other. I don't care if Dag1 fails, I still want to execute
Dag2. I also don't care about the execution order of the Dags.

Zsolt

2017-06-02 15:21 GMT+02:00 Scott Halgrim <[email protected]>:

> Try an ExternalTaskSensor
>
> Thanks,
>
> Scott
>
> On Jun 2, 2017, 3:28 AM -0700, Zsolt Tóth <[email protected]>,
> wrote:
> > Hi,
> >
> > is there a way to execute all tasks of a dag without interruption? Right
> > now the scheduler jumps between dags, and eventually they will all
> finish.
> > What I want is to force the scheduler to finish a dag completely, and
> jump
> > to the next one afterwards.
> > I think I could set all tasks of the dag to the same priority, giving
> each
> > dag a different prio this way, but then I'll also have a precedence
> between
> > DAGs, which I don't want.
> >
> > Thanks,
> > Zsolt
>

Reply via email to