+1 Thanks for volunteering! The calendar I have puts the cut date at August
29th, which looks to be 6 weeks from when 2.6.0 was cut. Do I have the
wrong calendar?

See:
https://calendar.google.com/calendar/embed?src=0p73sl034k80oob7seouanigd0%40group.calendar.google.com&ctz=America%2FLos_Angeles

Andrew

On Mon, Aug 20, 2018 at 11:43 AM Connell O'Callaghan <conne...@google.com>
wrote:

> +1 Charles thank you for taking this up and helping us maintain this
> schedule.
>
> On Mon, Aug 20, 2018 at 11:29 AM Charles Chen <c...@google.com> wrote:
>
>> Hey everyone,
>>
>> Our release calendar indicates that the process for the 2.7.0 Beam
>> release should start on September 7.
>>
>> I volunteer to perform this release and propose the following schedule:
>>
>>    - We start triaging issues in JIRA this week.
>>    - I will cut the initial 2.7.0 release branch on September 7.
>>    - After September 7, any blockers will need to be manually
>>    cherry-picked into the release branch.
>>    - After tests pass and blockers are fully addressed, I will move on
>>    and perform other release tasks.
>>
>> What do you think?
>>
>> Best,
>> Charles
>>
>