Blockers were resolved and fixes were cherry-picked to the release branch.
I'll continue the release process.

Thanks,
Cham

On Mon, Nov 26, 2018 at 10:50 AM Lukasz Cwik <[email protected]> wrote:

> I'm working on BEAM-6102 and after 12 hours on the issue I have not made
> much real progress. I initially suspected its a shading issue with the
> Dataflow worker jar but can't reproduce the issue without running a full
> Dataflow pipeline. Any help would be appreciated, context of what I have
> tried is on the JIRA and you can reach out to me on Slack.
>
> On Mon, Nov 26, 2018 at 9:50 AM Chamikara Jayalath <[email protected]>
> wrote:
>
>> Hi All,
>>
>> Currently there are two blockers for the 2.9.0 release.
>>
>> * Dataflow cannot deserialize DoFns -
>> https://issues.apache.org/jira/browse/BEAM-6102
>> * [SQL] Nexmark 5, 7 time out -
>> https://issues.apache.org/jira/browse/BEAM-6082
>>
>> We'll postpone cutting the release candidate till these issues are
>> resolved.
>>
>> Thanks,
>> Cham
>>
>>
>> On Wed, Nov 21, 2018 at 1:22 PM Kenneth Knowles <[email protected]> wrote:
>>
>>> You could `git checkout -b release-2.9.0 <known-good-hash>`. But
>>> cherrypicking fixes is also easy.
>>>
>>> Kenn
>>>
>>> On Wed, Nov 21, 2018 at 1:06 PM Chamikara Jayalath <[email protected]>
>>> wrote:
>>>
>>>> I went through Jenkins test suites and failures seems to be known
>>>> issues with JIRAs that are release blockers. So we'll cherry-pick fixes to
>>>> these.
>>>> In general though I think it might be hard to pick an exact "green"
>>>> time for cutting the release just by eyeballing since different test suites
>>>> run at different times.
>>>>
>>>> - Cham
>>>>
>>>>
>>>>
>>>> On Wed, Nov 21, 2018 at 12:59 PM Valentyn Tymofieiev <
>>>> [email protected]> wrote:
>>>>
>>>>> It looks like 2.9.0 branch includes commits from
>>>>> https://github.com/apache/beam/pull/7029, which break Python
>>>>> Postcommit Test suite. Rollback is in flight:
>>>>> https://github.com/apache/beam/pull/7107, and will need to be
>>>>> cherry-picked to release branch.
>>>>>
>>>>> I think we should try to adjust release branch cutting process so that
>>>>> all relevant test suites pass on the release branch when we cut it.
>>>>>
>>>>> On Wed, Nov 21, 2018 at 11:31 AM Chamikara Jayalath <
>>>>> [email protected]> wrote:
>>>>>
>>>>>> Release branch was cut:
>>>>>> https://github.com/apache/beam/tree/release-2.9.0
>>>>>> Please cherry-pick fixes to 2.9.0 blockers to this branch.
>>>>>>
>>>>>> Thanks,
>>>>>> Cham
>>>>>>
>>>>>> On Tue, Nov 20, 2018 at 9:00 PM Jean-Baptiste Onofré <[email protected]>
>>>>>> wrote:
>>>>>>
>>>>>>> Hi Cham,
>>>>>>>
>>>>>>> it sounds good to me.
>>>>>>>
>>>>>>> I'm resuming some works on IOs but nothing blocker.
>>>>>>>
>>>>>>> Regards
>>>>>>> JB
>>>>>>>
>>>>>>> On 21/11/2018 03:59, Chamikara Jayalath wrote:
>>>>>>> > Hi All,
>>>>>>> >
>>>>>>> > Looks like there are three blockers in the burndown list but they
>>>>>>> are
>>>>>>> > actively being worked on.
>>>>>>> >
>>>>>>> > If there's no objection I'll create the release branch tomorrow
>>>>>>> morning.
>>>>>>> > We can cherry-pick fixes to the blockers before building the first
>>>>>>> RC
>>>>>>> > hopefully on Monday.
>>>>>>> >
>>>>>>> > Thanks,
>>>>>>> > Cham
>>>>>>> >
>>>>>>> >
>>>>>>> > On Sat, Nov 17, 2018 at 10:38 AM Kenneth Knowles <[email protected]
>>>>>>> > <mailto:[email protected]>> wrote:
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >     On Fri, Nov 16, 2018, 18:25 Thomas Weise <[email protected]
>>>>>>> >     <mailto:[email protected]> wrote:
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >         On Thu, Nov 15, 2018 at 10:53 PM Charles Chen <
>>>>>>> [email protected]
>>>>>>> >         <mailto:[email protected]>> wrote:
>>>>>>> >
>>>>>>> >             +1
>>>>>>> >
>>>>>>> >             Note that we need to temporarily revert
>>>>>>> >             https://github.com/apache/beam/pull/6683 before the
>>>>>>> release
>>>>>>> >             branch cut per the discussion
>>>>>>> >             at
>>>>>>> https://lists.apache.org/thread.html/78fe33dc41b04886f5355d66d50359265bfa2985580bb70f79c53545@%3Cdev.beam.apache.org%3E
>>>>>>> >
>>>>>>> >
>>>>>>> >         Since it is for the release I would prefer this to be done
>>>>>>> in
>>>>>>> >         the release branch, and not in master.
>>>>>>> >
>>>>>>> >
>>>>>>> >     +1 do it (and all remaining burndown) on the release branch.
>>>>>>> >     Tracking Jira targeting 2.9.0?
>>>>>>> >
>>>>>>> >     Kenn
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >
>>>>>>> >             On Thu, Nov 15, 2018 at 9:18 PM Tim
>>>>>>> >             <[email protected]
>>>>>>> >             <mailto:[email protected]>> wrote:
>>>>>>> >
>>>>>>> >                 Thanks Cham
>>>>>>> >                 +1
>>>>>>> >
>>>>>>> >                 On 16 Nov 2018, at 05:30, Thomas Weise <
>>>>>>> [email protected]
>>>>>>> >                 <mailto:[email protected]>> wrote:
>>>>>>> >
>>>>>>> >>                 +1
>>>>>>> >>
>>>>>>> >>
>>>>>>> >>                 On Thu, Nov 15, 2018 at 4:34 PM Ahmet Altay
>>>>>>> >>                 <[email protected] <mailto:[email protected]>>
>>>>>>> wrote:
>>>>>>> >>
>>>>>>> >>                     +1 Thank you.
>>>>>>> >>
>>>>>>> >>                     On Thu, Nov 15, 2018 at 4:22 PM, Kenneth
>>>>>>> Knowles
>>>>>>> >>                     <[email protected] <mailto:[email protected]>>
>>>>>>> wrote:
>>>>>>> >>
>>>>>>> >>                         SGTM. Thanks for keeping track of the
>>>>>>> schedule.
>>>>>>> >>
>>>>>>> >>                         Kenn
>>>>>>> >>
>>>>>>> >>                         On Thu, Nov 15, 2018 at 1:59 PM Chamikara
>>>>>>> >>                         Jayalath <[email protected]
>>>>>>> >>                         <mailto:[email protected]>> wrote:
>>>>>>> >>
>>>>>>> >>                             Hi All,
>>>>>>> >>
>>>>>>> >>                             According to the release calendar [1]
>>>>>>> >>                             branch cut date for Beam 2.9.0
>>>>>>> release is
>>>>>>> >>                             11/21/2018. Since previous release
>>>>>>> branch
>>>>>>> >>                             was cut close to the respective
>>>>>>> calendar
>>>>>>> >>                             date I'd like to propose cutting
>>>>>>> release
>>>>>>> >>                             branch for 2.9.0 on 11/21/2018. Next
>>>>>>> week
>>>>>>> >>                             is Thanksgiving holiday in US and
>>>>>>> possibly
>>>>>>> >>                             some folks will be out so we can try
>>>>>>> to
>>>>>>> >>                             produce RC1 on Monday after
>>>>>>> (11/26/2018).
>>>>>>> >>                             We can attend to current blocker
>>>>>>> JIRAs [2]
>>>>>>> >>                             in the meantime.
>>>>>>> >>
>>>>>>> >>                             I'd like to volunteer to perform this
>>>>>>> release.
>>>>>>> >>
>>>>>>> >>                             WDYT ?
>>>>>>> >>
>>>>>>> >>                             Thanks,
>>>>>>> >>                             Cham
>>>>>>> >>
>>>>>>> >>                             [1]
>>>>>>> https://calendar.google.com/calendar/embed?src=0p73sl034k80oob7seouanigd0%40group.calendar.google.com&ctz=America%2FLos_Angeles
>>>>>>> >>                             [2]
>>>>>>> https://s.apache.org/beam-2.9.0-burndown
>>>>>>> >>
>>>>>>> >>
>>>>>>>
>>>>>>> --
>>>>>>> Jean-Baptiste Onofré
>>>>>>> [email protected]
>>>>>>> http://blog.nanthrax.net
>>>>>>> Talend - http://www.talend.com
>>>>>>>
>>>>>>

Reply via email to