Also the 2.29.0 was re-cut.

Usually a delay in one release should not delay the next release, because
each release represents a certain quantity of changes. But in this case,
the actual quantity of changes is affected by the re-cut, too.

On Wed, Apr 21, 2021 at 4:12 PM Heejong Lee <[email protected]> wrote:

> Update on the 2.30.0 branch cut schedule:
>
> I'm thinking of delaying the branch cut a week since I've got a few
> responses that some high priority changes are still ongoing.
>
> The new cut date is April 28.
>
>
> On Tue, Apr 20, 2021 at 6:07 PM Ahmet Altay <[email protected]> wrote:
>
>> +1 and thank you!
>>
>> On Tue, Apr 20, 2021 at 4:55 PM Heejong Lee <[email protected]> wrote:
>>
>>> Hi All,
>>>
>>> Beam 2.30.0 release is scheduled to be cut on April 21 according to the
>>> release calendar [1]
>>>
>>> I'd like to volunteer myself to be the release manager for this release.
>>> I plan on cutting the release branch on the scheduled date.
>>>
>>> Any comments or objections ?
>>>
>>> Thanks,
>>> Heejong
>>>
>>> [1]
>>> https://calendar.google.com/calendar/u/0/[email protected]&ctz=America/Los_Angeles
>>>
>>

Reply via email to