+1 [binding]

--Alex

> -----Original Message-----
> From: Will Chan [mailto:will.c...@citrix.com]
> Sent: Monday, June 3, 2013 11:08 AM
> To: dev@cloudstack.apache.org
> Subject: RE: [VOTE] Pushback 4.2.0 Feature Freeze
> 
> +1 [Binding]
> 
> It looks like there are a couple of last minute features that would make 4.1 a
> superb release.   I would say that we should not allow any new features that
> haven't already been proposed and that the extension does not go beyond 4
> weeks.  If beyond that, I'm a  -1.
> 
> Will
> 
> > -----Original Message-----
> > From: Chip Childers [mailto:chip.child...@sungard.com]
> > Sent: Friday, May 31, 2013 8:00 AM
> > To: dev@cloudstack.apache.org
> > Subject: [VOTE] Pushback 4.2.0 Feature Freeze
> >
> > Following our discussion on the proposal to push back the feature
> > freeze date for 4.2.0 [1], we have not yet achieved a clear consensus.
> Well...
> > we have already defined the "project rules" for figuring out what to do.
> > In out project by-laws [2], we have defined a "release plan" decision
> > as
> > follows:
> >
> > > 3.4.2. Release Plan
> > >
> > > Defines the timetable and work items for a release. The plan also
> > > nominates a Release Manager.
> > >
> > > A lazy majority of active committers is required for approval.
> > >
> > > Any active committer or PMC member may call a vote. The vote must
> > > occur on a project development mailing list.
> >
> > And our lazy majority is defined as:
> >
> > > 3.2.2. Lazy Majority - A lazy majority vote requires 3 binding +1
> > > votes and more binding +1 votes than binding -1 votes.
> >
> > Our current plan is the starting point, so this VOTE is a vote to
> > change the current plan.  We require a 72 hour window for this vote,
> > so IMO we are in an odd position where the feature freeze date is at
> > least extended until Tuesday of next week.
> >
> > Our current plan of record for 4.2.0 is at [3].
> >
> > [1] http://markmail.org/message/vi3nsd2yo763kzua
> > [2] http://s.apache.org/csbylaws
> > [3]
> > https://cwiki.apache.org/confluence/display/CLOUDSTACK/Cloudstack+4.2
> > +Release
> >
> > ----------------------------------------------------------------
> >
> > I'd like to call a VOTE on the following:
> >
> > Proposal: Extend the feature freeze date for our 4.2.0 feature release
> > from today (2013-05-31) to 2013-06-28.  All other dates following the
> > feature freeze date in the plan would be pushed out 4 weeks as well.
> >
> > Please respond with one of the following:
> >
> > +1 : change the plan as listed above
> > +/-0 : no strong opinion, but leaning + or -
> > -1 : do not change the plan
> >
> > This vote will remain open until Tuesday morning US eastern time.
> >
> > -chip