+1
>
> On December 11, 2018 at 8:09 PM Ed Cable <[email protected]> wrote:
>
> Hi all,
>
> This to continue the discussion on the planning of the 1.3 release. With
> the slight delays in 1.2, we're a little more than a week behind schedule
> for 1.3. The wiki page (
>
> https://cwiki.apache.org/confluence/display/FINERACT/1.3.0+-+Apache+Fineract)
> has been updated with the new schedule to reflect the following:
>
> QA: Dec 14 - 26
> Publish Release Notes: Dec 26
> Vote on Release: Jan 1
> Target Release Date: Jan 7
>
> The list of tickets that are ready to be merged or currently under
> development has been updated at 1.3.0. No additional tickets will be added
> to the scope of the 1.3.0 release - any new contributions that get raised
> will be targeted for the 1.4.0 release.
>
> Some of the enhancements to be included include the GSIM and GLIM work led
> by Nikil, performance enhancements including parallelization of batch jobs
> led by Kumaranath, and the notifications framework done previously by
> Courage.
>
> *Help the community out and build merit!*
> P1 bugs that couldn't be addressed during this release cycle have been
> tagged with 1.4.0 fix version. We welcome any volunteer contributors to
> work on some of these P1 issues.
>
> Once again, I ask that if you have a contribution that you've worked on or
> would like to make, please begin discussing it on-list so we can aim to
> get
> it into 1.4.0.
>
> The planned cutoff date for new features going into 1.4.0 is January 7.
> See
> more details at
>
> https://cwiki.apache.org/confluence/display/FINERACT/1.4.0+-+Apache+Fineract
>
> On Wed, Nov 21, 2018 at 9:56 AM Ed Cable <[email protected]> wrote:
>
> > >
> > Hello Community,
> >
> > Earlier in the year we discussed and adopted a schedule for
> > targeting
> > monthly releases. We're going to try and achieve that with the
> > forthcoming
> > 1.3 release.
> >
> > This email hearby kicks off the planning process for the Fineract
> > 1.3
> > release. I've included the table discussing what is occurring at
> > each phase
> > and how it differed from our previous processes.
> >
> > So between now and November 30, on this email thread and in JIRA
> > and the
> > release planning page, I want any individuals in the community
> > whether
> > you're a volunteer, an intern, or a partner that's built out
> > functionality,
> > to discuss and share if you have code that you would like to and
> > think it'd
> > be ready to contribute for the 1.3 release.
> >
> > The code should be near complete at this stage so if you do have a
> > contribute you want to make but it's still in progress, that can be
> > targeted for a future release, i.e. 1.4
> >
> > Please discuss on this thread, add to this wiki page or open and tag
> > tickets with the release fix version of 1.3.0
> >
> > Release Page on Wiki:
> >
> > https://cwiki.apache.org/confluence/display/FINERACT/1.3.0+-+Apache+Fineract
> > JIRA Filter for Issues Tagged 1.3.0:
> > https://issues.apache.org/jira/issues/?filter=12345265
> >
> > Plans for Release Apache Fineract 1.3
> >
> > Planning Release - Start Discussion on November 21
> >
> > Announce Release - Nov 30
> >
> > QA - Nov 30 - Dec 14
> >
> > Publish Release Notes - December 14
> >
> > Vote on Release - December 21
> >
> > Target release date - December 28
> >
> > Stage
> >
> > Description
> >
> > Proposed Length
> >
> > How Far in Advance of Release (Proposed)
> >
> > How Far in Advance of Release (Currently)
> >
> > Planning of Next Release
> >
> > Discuss with community what would like to ship in next release and
> > what
> > people could work on.
> >
> > Create fix version on JIRA to assign to.
> >
> > Action: modify existing email template to open up planning process,
> > schedule a meeting to discuss and set a tentative branching date
> > (i.e. 2
> > weeks later, if release date is a month past that).
> >
> > .
> >
> > 1 week
> >
> > 6 weeks
> >
> > Doesn’t Exist
> >
> > Announcement of Release
> >
> > Announce what is going to come in the release (should be 80% done at
> > least).
> >
> > Cut a release branch and freeze release branch and then develop
> > branch
> > can still have active work on it but only in rare cases might
> > anything
> > additional from develop
> >
> > Email out sharing release branch details
> >
> > 4 weeks prior
> >
> > 1 - 2 months
> >
> > QA
> >
> > QA begins on the release branch - staging Server setup
> >
> > Might fix some regression issues
> >
> > 1 - 2 weeks
> >
> > 4 weeks prior
> >
> > JIRA Sanitization/Publish RElease Notes
> >
> > Sanitize release documentation
> >
> > Create release notes and email community release information with
> > links.
> >
> > 2 weeks prior
> >
> > Vote
> >
> > Create artifacts, sign release, etc. Open up votes
> >
> > 1 week prior
> >
> > Release
> >
> > Tally up votes, announce, update websites and infrastructure with
> > new
> > release artifacts.
> >
> > >
> --
> *Ed Cable*
> President/CEO, Mifos Initiative
> [email protected] | Skype: edcable | Mobile: +1.484.477.8649
>
> *Collectively Creating a World of 3 Billion Maries | *http://mifos.org
> <http://facebook.com/mifos> <http://www.twitter.com/mifos>
>