Hi Robert,

Thanks for your detailed explanation.

At present, we are preparing or participating in Flink forward, so +1 for
appropriate extension of deadline.

Best,
Jingsong

On Mon, Oct 19, 2020 at 5:36 PM Kurt Young <ykt...@gmail.com> wrote:

> Can we change the freeze date to October 30th (Friday next week)? It would
> be helpful
> for us if we have 2 more days.
>
> Best,
> Kurt
>
>
> On Mon, Oct 19, 2020 at 5:00 PM Robert Metzger <rmetz...@apache.org>
> wrote:
>
> > Hi all,
> >
> > Dian and I would like to discuss a few items regarding the upcoming Flink
> > 1.12 feature freeze:
> >
> > *A) Exact feature freeze day*
> > So far, we've always said "end of October
> > <https://cwiki.apache.org/confluence/display/FLINK/1.12+Release>" for
> the
> > freeze. We propose (end of day CEST) October 28th (Wednesday next week)
> as
> > the feature freeze time.
> > We want to create RC0 on the day after the feature freeze, to make sure
> the
> > RC creation process is running smoothly, and to have a common testing
> > reference point.
> >
> >
> >
> > *B) What does feature freeze mean?*After the feature freeze, no new
> > features are allowed to be merged to master. Only bug fixes and
> > documentation improvements.
> > The release managers will revert new feature commits after the feature
> > freeze.
> > Rational: The goal of the feature freeze phase is to improve the system
> > stability by addressing known bugs. New features tend to introduce new
> > instabilities, which would prolong the release process.
> > If you need to merge a new feature after the freeze, please open a
> > discussion on the dev@ list. If there are no objections by a PMC member
> > within 48 (workday)hours, the feature can be merged.
> >
> > *C) When to cut the "release-1.12" branch off master?*
> > In the last feature freeze, we had a pretty lengthy phase of maintaining
> > the "master" and "release-1.11" branches with the same fixes. Therefore,
> I
> > would like to propose an adjustment to the release process: We will have
> a
> > stabilization phase on master, between the feature freeze and the branch
> > cut.
> > I expect this stabilization phase to last between 1 and 3 weeks,
> depending
> > on the issues we find. Once all blockers are resolved, and no new
> blockers
> > are surfacing, we can cut off the "release-1.12" branch and finalize the
> > release.
> > Is anybody in the community waiting for the cut off to happen sooner so
> > that they can merge a big feature to Flink 1.13 ? (if that would be the
> > case, then we can not have a stabilization phase)
> >
> >
> > Let me know what you think!
> >
> > Best,
> > Dian and Robert
> >
>


-- 
Best, Jingsong Lee