On Aug 4, 2007, at 1:20 AM, Sander Temme wrote:


On Aug 3, 2007, at 9:21 AM, Jim Jagielski wrote:

Lets shoot for a T&R of 1.3, 2.0 and 2.2 on Aug 10th... That
means a possible release on the 13th. That way, admins
aren't compelled to upgrade before/during the weekend (other-
wise, T&R on the 8th and release on the 10th would make
sense)

I volunteer to RM 1.3 and even 2.2.

afaict, 1.3 and 2.0 are ready to go; we just have some
outstanding potentials still in line for 2.2

I keep volunteering for this, and keep dropping the ball. I agree with the schedule, but wouldn't we also give the folks who pull down the RCs some time in the office to kick the tires? Perhaps take an extra day and release on the 14th?


Sounds good.

I would renew my offer to RM but realistically I'll be traveling on the 10th so it's not unlikely that I'd drop the ball yet again.

S.

--
Sander Temme
[EMAIL PROTECTED]
PGP FP: 51B4 8727 466A 0BC3 69F4  B7B8 B2BE BC40 1529 24AF




Reply via email to