I do not think we should perform clean-up tasks in minor releases,
especially breaking ones, even in labs.  Of course on master this is a
desired and valuable change which recognizes the GCE as a high-quality
and blessed provider.  I also do not think we should delay releases for
anything other than regressions -- we will have another minor release
soon enough.

On Fri, Oct 03, 2014 at 09:36:54AM -0600, Chris Custine wrote:
> I suppose this is a good opportunity to discuss gce and oauth 
> (https://issues.apache.org/jira/browse/JCLOUDS-172).
> 
> There was some debate over whether we should graduate labs projects in a 
> patch release such as 1.8.1 (comments on JCLOUDS-172), but it seems like most 
> everyone is ok with it and I want to make sure that this topic gets resolved.
> 
> On the other hand, there have been some issues with GCE API in the last few 
> weeks which have cast some doubt on graduating from labs right now.  I think 
> they are rather minor issues, but the versioned GCE API changing from the 
> docs and previous return data makes this worthy of a discussion. 
> 
> For my 2 cents, I would say that fixing these issues, merging some stale PRs, 
> and releasing this in jclouds 1.8.1 on Monday is pushing my sensibility.  If 
> we were to hold off on the release another week or so, my comfort level would 
> be much better.  I’m not arguing to push back the release at all, just 
> putting out the options.
> 
> Thoughts?
> 
> Thanks,
> Chris
> -- 
> Chris Custine
> 
> 
> On October 2, 2014 at 10:12:29 AM, Everett Toews 
> (everett.to...@rackspace.com) wrote:
> 
> Let's schedule the release of 1.8.1.  
> 
> All code into 1.8.x by Monday, Oct. 6 EOD  
> Begin release on Tuesday, Oct. 7  
> 
> Can someone volunteer to do the actual release steps?  
> 
> I'll be catching up with work stuff all next week after being on the road for 
> a few weeks but I can do it if necessary.  
> 
> Thanks,  
> Everett  
> 

-- 
Andrew Gaul
http://gaul.org/