Thanks for your patience, Ommia!

Omnia Ibrahim <[email protected]> 於 2026年6月10日週三 下午6:59寫道:

> Okay seems like the final plan going with option 1 I have updated the
> 4.4.0 release dates with the final dates.
>
> Now the KIP freeze is set for 8th July
>
> Thanks everyone!
>
> > On 8 Jun 2026, at 07:06, Chia-Ping Tsai <[email protected]> wrote:
> >
> > Hi Omnia,
> >
> > Thanks for putting these options together. +1 for Opt-1.
> >
> > BTW, assuming the 3+2 schedule, the code freeze for 4.5.0 under Option 1
> should be Nov 18 rather than Nov 25.
> >
> > Also, this means we will seamlessly transition into our ideal new
> cadence of 3 releases a year, with target release dates landing nicely in
> January, May, and August.
> >
> > Best,
> > Chia-Ping
> >
> > On 2026/06/05 16:57:34 Omnia Ibrahim wrote:
> >> Hi all,
> >>
> >> There have been a few different opinions on the 4.4 schedule and as
> release manager I need to put the final dates. I'd like to lock this in
> early so please cast your vote below.
> >>
> >> The two proposals are below along with a visualisation of both 4.4
> timelines and the downstream impact on 4.5.
> >>
> >> 1. Delay 4.4 by few weeks  with 3+2+4
> >> KIP freeze        =                                                8th
> July  2026 (2nd Wed)
> >> Feature freeze = KIP freeze        + 3 weeks == 29th July 2026
> >> Code freeze     = Feature freeze + 2 weeks == 12th Aug 2026
> >> Release target = Code freeze     + 4 weeks == 9th Sep 2026
> >>
> >> 4.5 impact: 4.5 KIP freeze would start Q4 2026 (around 14 Oct), with a
> release target in Q1 2027 (around 20 Jan). This makes 4.5 a structurally
> longer release — the gap between code freeze (25 Nov) and release target is
> approximately 8 weeks, absorbing the holiday period.
> >>
> >>
> >> 2. Push 4.4 to be the last release in 2026 by target Oct for release
> target with 3+3+4 only for this one— This means KIP freeze start end of
> July 2026
> >>
> >> KIP freeze       =
> 29th July 2026
> >> Feature freeze = KIP freeze       + 3 weeks == 19th Aug 2026
> >> Code freeze     = Feature freeze + 3 weeks == 9th Sep 2026
> >> Release target = Code freeze     + 4 weeks == 7th Oct 2026
> >> The FF→CF window is 3 weeks rather than 2 (as in Option 1) to give the
> community more stabilisation time, given how tight the cadence has been
> this year.
> >>
> >> 4.5 impact: 4.5 KIP freeze starts 11 Nov 2026 (2nd Wed of November),
> code freeze lands 23 Dec 2026, and release target is 20 Jan 2027. The
> community takes the holiday break between code freeze and release — RC
> validation resumes in January with no pressure to deliver over the break.
> >>
> >> 
> >> Please reply with:
> >>
> >> +1 for Opt-1 — Option 1 (3+2+4, release 9 Sep 2026)
> >> +1 for Opt-2 — Option 2 (3+3+4, release 7 Oct 2026)
> >> 0 — No strong preference
> >> Vote closes Tuesday 9 Jun 2026 at 23:00 UTC. I will tally and post the
> result.
> >>
> >> I personally vote +1 for Opt-2.
> >>
> >> Best, Omnia
> >>
> >>> On 4 Jun 2026, at 09:32, Lucas Brutschy via dev <[email protected]>
> wrote:
> >>>
> >>> I'm not sure I have a good overview of all the different proposals,
> >>> but I'd vote for Omnia's first proposal: push back the 4.4.0 KIP
> >>> freeze to early July, target a September release, and have the 4.5.0
> >>> freezes this year and target the release date in January, and start
> >>> using Matthias' proposed schedule with 4.6.0.
> >>>
> >>> Cheers,
> >>> Lucas
> >>>
> >>> On Wed, Jun 3, 2026 at 11:38 PM <[email protected]> wrote:
> >>>>
> >>>>> In general, a 3+2+4 schedule was favored on the other thread, so I
> would think using it would be good?
> >>>>
> >>>> I know this is the favourite one on the other thread but I am
> thinking of making exception for 4.4 and adopt the preferred one from 4.5
> so we have 4.4 target for Oct and 4.5 target is Q1 2027
> >>>>
> >>>> WDYT?
> >>>>
> >>>> Sent from my iPhone
> >>>>
> >>>>> On 3 Jun 2026, at 17:04, Matthias J. Sax <[email protected]> wrote:
> >>>>>
> >>>>> Yes, I meant 2026 and 2027... somehow lagged a year :D
> >>>>>
> >>>>>
> >>>>> In general, a 3+2+4 schedule was favored on the other thread, so I
> would think using it would be good?
> >>>>>
> >>>>> For KIP freeze date, seems we have many different proposals
> >>>>> - Jun/15 (Monday)
> >>>>> - July/1st (Wednesday)
> >>>>> - July/8th (Wednesday)
> >>>>> - July/15th (Wednesday)
> >>>>> - July/29 (Wednesday)
> >>>>>
> >>>>> Maybe we should pick something in the middle like July/1st or
> July/8th as a compromise?
> >>>>>
> >>>>>
> >>>>> -Matthias
> >>>>>
> >>>>> On 6/3/26 8:29 AM, Chia-Ping Tsai wrote:
> >>>>>>>> Omnia Ibrahim <[email protected]> 於 2026年6月3日 晚上8:50 寫道:
> >>>>>>>
> >>>>>>> KIP freeze       =
>   29th July 2026
> >>>>>>> Feature freeze = KIP freeze         + 3 weeks == 19th Aug 2026
> >>>>>>> Code freeze     = Feature freeze + 3 weeks == 9th Sep 2026
> >>>>>>> Release target = Code freeze     + 4 weeks == 7th Oct 2026
> >>>>>> +1 to this plan, allowing us to adopt the new schedule starting
> from 4.5.0 I just realize how rushed our previous releases were in this
> year. Our Kafka community is by far the most productive I’d say
> >>>>>> Best,
> >>>>>> Chia-Ping
> >>>>>
> >>
> >>
>
>