Okay seems like the final plan going with option 1 I have updated the 4.4.0 release dates with the final dates.
Now the KIP freeze is set for 8th July Thanks everyone! > On 8 Jun 2026, at 07:06, Chia-Ping Tsai <[email protected]> wrote: > > Hi Omnia, > > Thanks for putting these options together. +1 for Opt-1. > > BTW, assuming the 3+2 schedule, the code freeze for 4.5.0 under Option 1 > should be Nov 18 rather than Nov 25. > > Also, this means we will seamlessly transition into our ideal new cadence of > 3 releases a year, with target release dates landing nicely in January, May, > and August. > > Best, > Chia-Ping > > On 2026/06/05 16:57:34 Omnia Ibrahim wrote: >> Hi all, >> >> There have been a few different opinions on the 4.4 schedule and as release >> manager I need to put the final dates. I'd like to lock this in early so >> please cast your vote below. >> >> The two proposals are below along with a visualisation of both 4.4 timelines >> and the downstream impact on 4.5. >> >> 1. Delay 4.4 by few weeks with 3+2+4 >> KIP freeze = 8th July >> 2026 (2nd Wed) >> Feature freeze = KIP freeze + 3 weeks == 29th July 2026 >> Code freeze = Feature freeze + 2 weeks == 12th Aug 2026 >> Release target = Code freeze + 4 weeks == 9th Sep 2026 >> >> 4.5 impact: 4.5 KIP freeze would start Q4 2026 (around 14 Oct), with a >> release target in Q1 2027 (around 20 Jan). This makes 4.5 a structurally >> longer release — the gap between code freeze (25 Nov) and release target is >> approximately 8 weeks, absorbing the holiday period. >> >> >> 2. Push 4.4 to be the last release in 2026 by target Oct for release target >> with 3+3+4 only for this one— This means KIP freeze start end of July 2026 >> >> KIP freeze = 29th >> July 2026 >> Feature freeze = KIP freeze + 3 weeks == 19th Aug 2026 >> Code freeze = Feature freeze + 3 weeks == 9th Sep 2026 >> Release target = Code freeze + 4 weeks == 7th Oct 2026 >> The FF→CF window is 3 weeks rather than 2 (as in Option 1) to give the >> community more stabilisation time, given how tight the cadence has been this >> year. >> >> 4.5 impact: 4.5 KIP freeze starts 11 Nov 2026 (2nd Wed of November), code >> freeze lands 23 Dec 2026, and release target is 20 Jan 2027. The community >> takes the holiday break between code freeze and release — RC validation >> resumes in January with no pressure to deliver over the break. >> >>  >> Please reply with: >> >> +1 for Opt-1 — Option 1 (3+2+4, release 9 Sep 2026) >> +1 for Opt-2 — Option 2 (3+3+4, release 7 Oct 2026) >> 0 — No strong preference >> Vote closes Tuesday 9 Jun 2026 at 23:00 UTC. I will tally and post the >> result. >> >> I personally vote +1 for Opt-2. >> >> Best, Omnia >> >>> On 4 Jun 2026, at 09:32, Lucas Brutschy via dev <[email protected]> >>> wrote: >>> >>> I'm not sure I have a good overview of all the different proposals, >>> but I'd vote for Omnia's first proposal: push back the 4.4.0 KIP >>> freeze to early July, target a September release, and have the 4.5.0 >>> freezes this year and target the release date in January, and start >>> using Matthias' proposed schedule with 4.6.0. >>> >>> Cheers, >>> Lucas >>> >>> On Wed, Jun 3, 2026 at 11:38 PM <[email protected]> wrote: >>>> >>>>> In general, a 3+2+4 schedule was favored on the other thread, so I would >>>>> think using it would be good? >>>> >>>> I know this is the favourite one on the other thread but I am thinking of >>>> making exception for 4.4 and adopt the preferred one from 4.5 so we have >>>> 4.4 target for Oct and 4.5 target is Q1 2027 >>>> >>>> WDYT? >>>> >>>> Sent from my iPhone >>>> >>>>> On 3 Jun 2026, at 17:04, Matthias J. Sax <[email protected]> wrote: >>>>> >>>>> Yes, I meant 2026 and 2027... somehow lagged a year :D >>>>> >>>>> >>>>> In general, a 3+2+4 schedule was favored on the other thread, so I would >>>>> think using it would be good? >>>>> >>>>> For KIP freeze date, seems we have many different proposals >>>>> - Jun/15 (Monday) >>>>> - July/1st (Wednesday) >>>>> - July/8th (Wednesday) >>>>> - July/15th (Wednesday) >>>>> - July/29 (Wednesday) >>>>> >>>>> Maybe we should pick something in the middle like July/1st or July/8th as >>>>> a compromise? >>>>> >>>>> >>>>> -Matthias >>>>> >>>>> On 6/3/26 8:29 AM, Chia-Ping Tsai wrote: >>>>>>>> Omnia Ibrahim <[email protected]> 於 2026年6月3日 晚上8:50 寫道: >>>>>>> >>>>>>> KIP freeze = >>>>>>> 29th July 2026 >>>>>>> Feature freeze = KIP freeze + 3 weeks == 19th Aug 2026 >>>>>>> Code freeze = Feature freeze + 3 weeks == 9th Sep 2026 >>>>>>> Release target = Code freeze + 4 weeks == 7th Oct 2026 >>>>>> +1 to this plan, allowing us to adopt the new schedule starting from >>>>>> 4.5.0 I just realize how rushed our previous releases were in this year. >>>>>> Our Kafka community is by far the most productive I’d say >>>>>> Best, >>>>>> Chia-Ping >>>>> >> >>