Okay seems like the final plan going with option 1 I have updated the 4.4.0 
release dates with the final dates. 

Now the KIP freeze is set for 8th July 

Thanks everyone!

> On 8 Jun 2026, at 07:06, Chia-Ping Tsai <[email protected]> wrote:
> 
> Hi Omnia,
> 
> Thanks for putting these options together. +1 for Opt-1.
> 
> BTW, assuming the 3+2 schedule, the code freeze for 4.5.0 under Option 1 
> should be Nov 18 rather than Nov 25.
> 
> Also, this means we will seamlessly transition into our ideal new cadence of 
> 3 releases a year, with target release dates landing nicely in January, May, 
> and August.
> 
> Best,
> Chia-Ping
> 
> On 2026/06/05 16:57:34 Omnia Ibrahim wrote:
>> Hi all,
>> 
>> There have been a few different opinions on the 4.4 schedule and as release 
>> manager I need to put the final dates. I'd like to lock this in early so 
>> please cast your vote below.
>> 
>> The two proposals are below along with a visualisation of both 4.4 timelines 
>> and the downstream impact on 4.5.
>> 
>> 1. Delay 4.4 by few weeks  with 3+2+4
>> KIP freeze        =                                                8th July  
>> 2026 (2nd Wed)
>> Feature freeze = KIP freeze        + 3 weeks == 29th July 2026
>> Code freeze     = Feature freeze + 2 weeks == 12th Aug 2026
>> Release target = Code freeze     + 4 weeks == 9th Sep 2026
>> 
>> 4.5 impact: 4.5 KIP freeze would start Q4 2026 (around 14 Oct), with a 
>> release target in Q1 2027 (around 20 Jan). This makes 4.5 a structurally 
>> longer release — the gap between code freeze (25 Nov) and release target is 
>> approximately 8 weeks, absorbing the holiday period.
>> 
>> 
>> 2. Push 4.4 to be the last release in 2026 by target Oct for release target 
>> with 3+3+4 only for this one— This means KIP freeze start end of July 2026
>> 
>> KIP freeze       =                                                  29th 
>> July 2026 
>> Feature freeze = KIP freeze       + 3 weeks == 19th Aug 2026
>> Code freeze     = Feature freeze + 3 weeks == 9th Sep 2026
>> Release target = Code freeze     + 4 weeks == 7th Oct 2026
>> The FF→CF window is 3 weeks rather than 2 (as in Option 1) to give the 
>> community more stabilisation time, given how tight the cadence has been this 
>> year.
>> 
>> 4.5 impact: 4.5 KIP freeze starts 11 Nov 2026 (2nd Wed of November), code 
>> freeze lands 23 Dec 2026, and release target is 20 Jan 2027. The community 
>> takes the holiday break between code freeze and release — RC validation 
>> resumes in January with no pressure to deliver over the break.
>> 
>> 
>> Please reply with:
>> 
>> +1 for Opt-1 — Option 1 (3+2+4, release 9 Sep 2026)
>> +1 for Opt-2 — Option 2 (3+3+4, release 7 Oct 2026)
>> 0 — No strong preference
>> Vote closes Tuesday 9 Jun 2026 at 23:00 UTC. I will tally and post the 
>> result.
>> 
>> I personally vote +1 for Opt-2.
>> 
>> Best, Omnia
>> 
>>> On 4 Jun 2026, at 09:32, Lucas Brutschy via dev <[email protected]> 
>>> wrote:
>>> 
>>> I'm not sure I have a good overview of all the different proposals,
>>> but I'd vote for Omnia's first proposal: push back the 4.4.0 KIP
>>> freeze to early July, target a September release, and have the 4.5.0
>>> freezes this year and target the release date in January, and start
>>> using Matthias' proposed schedule with 4.6.0.
>>> 
>>> Cheers,
>>> Lucas
>>> 
>>> On Wed, Jun 3, 2026 at 11:38 PM <[email protected]> wrote:
>>>> 
>>>>> In general, a 3+2+4 schedule was favored on the other thread, so I would 
>>>>> think using it would be good?
>>>> 
>>>> I know this is the favourite one on the other thread but I am thinking of 
>>>> making exception for 4.4 and adopt the preferred one from 4.5 so we have 
>>>> 4.4 target for Oct and 4.5 target is Q1 2027
>>>> 
>>>> WDYT?
>>>> 
>>>> Sent from my iPhone
>>>> 
>>>>> On 3 Jun 2026, at 17:04, Matthias J. Sax <[email protected]> wrote:
>>>>> 
>>>>> Yes, I meant 2026 and 2027... somehow lagged a year :D
>>>>> 
>>>>> 
>>>>> In general, a 3+2+4 schedule was favored on the other thread, so I would 
>>>>> think using it would be good?
>>>>> 
>>>>> For KIP freeze date, seems we have many different proposals
>>>>> - Jun/15 (Monday)
>>>>> - July/1st (Wednesday)
>>>>> - July/8th (Wednesday)
>>>>> - July/15th (Wednesday)
>>>>> - July/29 (Wednesday)
>>>>> 
>>>>> Maybe we should pick something in the middle like July/1st or July/8th as 
>>>>> a compromise?
>>>>> 
>>>>> 
>>>>> -Matthias
>>>>> 
>>>>> On 6/3/26 8:29 AM, Chia-Ping Tsai wrote:
>>>>>>>> Omnia Ibrahim <[email protected]> 於 2026年6月3日 晚上8:50 寫道:
>>>>>>> 
>>>>>>> KIP freeze       =                                                  
>>>>>>> 29th July 2026
>>>>>>> Feature freeze = KIP freeze         + 3 weeks == 19th Aug 2026
>>>>>>> Code freeze     = Feature freeze + 3 weeks == 9th Sep 2026
>>>>>>> Release target = Code freeze     + 4 weeks == 7th Oct 2026
>>>>>> +1 to this plan, allowing us to adopt the new schedule starting from 
>>>>>> 4.5.0 I just realize how rushed our previous releases were in this year. 
>>>>>> Our Kafka community is by far the most productive I’d say
>>>>>> Best,
>>>>>> Chia-Ping
>>>>> 
>> 
>> 

Reply via email to