At the moment, the relationship is the wrong way around - the release plugin
should contact the SCM. That's my fault. I didn't want to mess with the
existing release plugin other than to reuse the POM transformer inside
there.

Jason is currently working on the release process as well, so I think we
should all "sit down" and work out some requirements together with anyone
else interested. Between the 3 of us we seem to have a lot of the different
use cases covered in the workflow area.

scm:prepare-release and scm:perform-release do most of what I need for the
moment (although JIRA/Bugzilla integration would be really nice!)

Cheers,
Brett

> -----Original Message-----
> From: Vincent Massol [mailto:[EMAIL PROTECTED] 
> Sent: Monday, 3 May 2004 4:13 PM
> To: 'Maven Developers List'
> Subject: RE: Little glitches in rc2 release process
> 
> 
> I am not very clear about this: so we use the scm plugin for 
> performing releases? But not the release plugin, right? 
> What's the goal? To modify and use the release plugin in the 
> future? (makes more sense to me - the name is great!).
> 
> I'm asking because I was planning to work on the release 
> process and release plugin in the near future (but not before 1 week).
> 
> Thanks
> -Vincent
> 
> > -----Original Message-----
> > From: Brett Porter [mailto:[EMAIL PROTECTED]
> > Sent: 03 May 2004 07:59
> > To: 'Maven Developers List'
> > Subject: RE: Little glitches in rc2 release process
> > 
> > > > A bug in the changes plugin, already fixed.
> > >
> > > What's the relationship with the changes plugin?
> > >
> > 
> > Sorry, I meant release plugin.
> > 
> > scm:prepare-release utilises changes to transform changes 
> and release
> to
> > transform the POM.
> > 
> > - Brett
> 
> 
> 
> ---------------------------------------------------------------------
> To unsubscribe, e-mail: [EMAIL PROTECTED]