A number of the tickets are low complexity.  So anyone with some spare
cycles in the next two weeks, please jump in and claim a ticket!

See the top-left box on the sprint jira dashboard:
https://tickets.openmrs.org/secure/Dashboard.jspa?selectPageId=11050

Ben

On Fri, Nov 18, 2011 at 4:56 AM, Darius Jazayeri <[email protected]>wrote:

> Hi Daniel,
>
> I went through the sprint tickets, and removed a few, and changed the
> priorities of others.
>
> Currently we have 38 sprint tickets, of which:
>
>    - 10 Ready for Work
>       - 2 x Should
>       - 6 x Could
>       - 2 x Non-Essential
>    - 8 In Progress
>       - 1 x Blocker
>       - 1 x Must
>       - 2 x Should
>       - 3 x Could
>       - 1 x Non-Essential
>    - 18 Needs Review
>
> This should be doable during the sprint, but we're going to need to keep
> people focused on priorities.
>
> The guideline I used was that any bug pre-dating 1.9 is at most a "Could"
> for this sprint. Our top priorities are hardening the new functionality
> introduced in 1.9, and getting rid of any bugs introduced in 1.9.
>
> But I just took lots of bugs that really need to get fixed, and made them
> only "Could". We really need to do a bugfixing sprint or two soon.
>
> -Darius
> ------------------------------
> Click here to 
> unsubscribe<[email protected]?body=SIGNOFF%20openmrs-devel-l>from 
> OpenMRS Developers' mailing list

_________________________________________

To unsubscribe from OpenMRS Developers' mailing list, send an e-mail to 
[email protected] with "SIGNOFF openmrs-devel-l" in the  body (not 
the subject) of your e-mail.

[mailto:[email protected]?body=SIGNOFF%20openmrs-devel-l]

Reply via email to