Following up on this after watching today's community call replay. Dave made 
the point that the big chunk of work toward this release is writing release 
notes and deciding which of the components is ready. Several people volunteered 
(Carlos, Matt) and I’m volunteering myself as well.

I’d suggest we create an issue for each repo that we will include in the 
release to deliver the release notes to start.

Dave also pointed out that there’s a few staging phases to coordinate which 
could take us about 3 weeks (largely because of the voting and 72hr waiting 
periods).

Dave: what else did I miss? 

-r

> On Jan 7, 2019, at 4:55 PM, David P Grove <[email protected]> wrote:
> 
> 
> 
> I would like to see us push out a consolidated next release in the near
> future (by end of January?).  I'd also like to see us attempt to establish
> a regular cadence of such consolidated releases (perhaps quarterly?).
> 
> We would start this release from the leaves of our dependency tree and work
> up:
>       1) release all action runtimes that have changed since their last
> Apache release.
>       2) release cli tooling
>       3) release event providers
>       4) release core system (with pinned versions of runtimes, cli, and
> providers)
>       5) release packaging projects (kube-deploy, dev-tools, etc.) with
> pinned versions of entire system.
> 
> I would also like to propose that although we keep semantic versioning of
> the sub-packages (openwhisk-runtime-java-x.y.z, openwhisk-cli-a.b.c, etc),
> that we adopt a date-based version number for the consolidate uber-release
> (eg OpenWhisk 19.01 if we actually manage to get this all out in January).
> 
> Opinions?
> 
> --dave