Pig's progress estimation should account for parallel job executions
--------------------------------------------------------------------

                 Key: PIG-1883
                 URL: https://issues.apache.org/jira/browse/PIG-1883
             Project: Pig
          Issue Type: Improvement
            Reporter: Laukik Chitnis
            Assignee: Laukik Chitnis
             Fix For: 0.9.0


Currently, Pig's progress estimation is based on the percentage of jobs 
completed out of the total number of MR jobs. However, since the MR operators 
are arranged in a DAG (and hence more than 1 job might be submitted for 
execution in parallel), the progress estimation can be improved by considering 
the number of jobs in the critical path, instead of just the total number of 
jobs.

-- 