Hi folks,

As we know from experience, that the first release needs some careful
preparation steps, I would like to propose aiming for the Apache
Polaris release by the end of October (after CoC NA).

I propose to start from 0.1-incubating (currently we are building
999-SNAPSHOT :) ).
I already created 0.1 milestone on GitHub. We can rename it if needed.

The preparation steps would be:
- do the triage on the GitHub issues, assigning issues to the 0.1 milestone
- check the legal (LICENSE, NOTICE, DISCLAIMER, KEYS, etc). I will
start some new checks/updates on that (as I have some experience :) ).
- check distribution and artifact publication (dist.apache.org,
repository.apache.org, ...)

I have several PRs in preparation, including the release preparation
related PRs.

As reminder about the process
(https://incubator.apache.org/guides/releasemanagement.html), we need
to do release "internally" to the podling , and then start "again" the
vote on the incubator general mailing list. So it's a "longer" process
comparing to a TLP release.

What do you think ?

Thanks,
Regards
JB