Hi Tora,
I meant that two different tests were:
http://wiki.services.openoffice.org/wiki/OOoRelease21
...
- TCM l10n testing on CWS builds: November 2nd - 8th
...
- release candidate for all languages: November 23th 2006
I cannot see any word "test" or QA test in the second instance, can you?
I mean you should probably use TCM, and this is a single, unified
process, not two processes. This is how I understood it: if there are no
stoppers discovered in TCM tests, or testtool tests, simply give a go to
the release process. But this is the first time anyone is doing full QA
for Polish builds, and I could be wrong about that.
We were not using TCM before but I wouldn't call that formal testing or
QA at all. This was just random checking of various features before
releasing unofficial builds.
Best,
Marcin
---------------------------------------------------------------------