Hi, It's unclear to me how to handle a release vote when the artifacts are changed during the vote. E.g.
- start release on 2015-04-01 - a problem is discovered on 2015-04-02 - the problem is fixed on 2015-04-03 Is it OK to continue with the vote or do we mandate that the vote is cancelled? If we decide it's OK to continue with the vote we also need to decide what to do with: - +1 votes on the previous artifacts ( probably ignore ) - -1 votes on the previous artifacts ( probably keep as vetos unless the voter withdraws/recasts the vote ) - the duration of the vote ( probably restart the 72 hours count ) I don't have a very strong opinion about this, but I would be less confused if releases were immutable :-) and any change of the artifacts under vote would mean cancelling the vote and starting a new one. But I'm happy to do what works for everyone, given what we have clear rules for it. Cheers, Robert
