Hi all,
The following is my very rough plan for the September releases:
- Mon 31/08 - Public Holiday
- Tue 01/09 - Complete native C changes
- Wed 02/09 - Complete Java side of native changes
- Thu 03/09 - Test native, tag, create RC, start VOTE
- Fri 04/09 - Tomcat release prep
- Mon 07/09 - Tomcat release prep
- Tue 08/09 - Tomcat release prep
- Wed 09/09 - Release Native, Tag 11.0.x, start VOTE
- Thu 10/09 - ?
- Fri 11/09 - ?
- Mon 14/09 - Release 11.0.x
I think there is some slack in that plan but I suspect circumstances
will conspire to find things to use up the slack.
Mark
---------------------------------------------------------------------