On 8/28/26 1:44 PM, Mark Thomas wrote:
Hi all,
The following is my very rough plan for the September releases:
- Mon 31/08 - Public Holiday
- Tue 01/09 - Complete native C changes
- Wed 02/09 - Complete Java side of native changes
- Thu 03/09 - Test native, tag, create RC, start VOTE
- Fri 04/09 - Tomcat release prep
- Mon 07/09 - Tomcat release prep
- Tue 08/09 - Tomcat release prep
- Wed 09/09 - Release Native, Tag 11.0.x, start VOTE
- Thu 10/09 - ?
- Fri 11/09 - ?
- Mon 14/09 - Release 11.0.x
I think there is some slack in that plan but I suspect circumstances
will conspire to find things to use up the slack.
Sounds good to me.
I'll be out for the US Labor Day holiday starting (checks watch) NOW and
I'll be back Tuesday morning September 8th.
-chris
---------------------------------------------------------------------