Hi,

I've started the page at 
http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap 
  but let's discuss it here first.

So what are the tasks we want to solve for 1.5. Here's my take:

     * More bug fixes
     * Better performance
           o Run XE with a profiler and find bottlenecks
           o Reduce number of database calls
           o Improved page loading
     * More automated tests
           o More selenium tests
           o Add tests on Tomcat 6.x as part of the CI build
           o Add tests on Windows and with IE6 and IE7 as part of the  
CI build
     * Overhaul of the Administration

So basically more stability and more usability.

In term of dates, I think 2 milestones followed by a RC works pretty  
well. In total that's about 3 weeks for each milestone and then 1 week  
for each RC. If we imagine we need 2, then that's 8 weeks, i.e. 2  
months, which sounds good to me.

WDYT?

I'll let JV propose precise dates.

Thanks
-Vincent