Vincent Massol wrote:
> Hi,
> 
> I've started the page at 
> http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap 
>   but let's discuss it here first.
> 
> So what are the tasks we want to solve for 1.5. Here's my take:
> 
>      * More bug fixes
>      * Better performance
>            o Run XE with a profiler and find bottlenecks
>            o Reduce number of database calls
>            o Improved page loading
>      * More automated tests
>            o More selenium tests
>            o Add tests on Tomcat 6.x as part of the CI build
>            o Add tests on Windows and with IE6 and IE7 as part of the  
> CI build
>      * Overhaul of the Administration
> 
> So basically more stability and more usability.

I won't have much time for the 1.5 release, so I don't have anything 
else to add. I'll try to improve the documentation during this release 
cycle.

> In term of dates, I think 2 milestones followed by a RC works pretty  
> well. In total that's about 3 weeks for each milestone and then 1 week  
> for each RC. If we imagine we need 2, then that's 8 weeks, i.e. 2  
> months, which sounds good to me.
> 
> WDYT?
> 
> I'll let JV propose precise dates.
> 


-- 
Sergiu Dumitriu
http://purl.org/net/sergiu/
_______________________________________________
devs mailing list
[email protected]
http://lists.xwiki.org/mailman/listinfo/devs

Reply via email to