In order to try meet a release date, I would like to use the process as documented here:
http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1 Synopsis: June 4th: * send 2 day warning mail, ask if anyone needs to block the release. * branch stable-4.1.x to allow 4.2 development to continue. June 6th: * build staged release. * send out call for testing. * do release on jira with release post-dated to the 11th. June 11th: * release from staging. * publish release. I know this is a tight schedule but realistically we need 2 days for warning/stabilization and 2 (working) days for testing. WDYT? Caleb _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs