In order to try meet a release date, I would like to use the process as 
documented here:

http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1

Synopsis:

June 4th:
    * send 2 day warning mail, ask if anyone needs to block the release.
    * branch stable-4.1.x to allow 4.2 development to continue.

June 6th:
    * build staged release.
    * send out call for testing.
    * do release on jira with release post-dated to the 11th.

June 11th:
    * release from staging.
    * publish release.


I know this is a tight schedule but realistically we need 2 days for 
warning/stabilization
and 2 (working) days for testing.

WDYT?

Caleb