On Jun 1, 2012, at 4:51 AM, Sergiu Dumitriu wrote:

> On 05/31/2012 12:54 PM, Caleb James DeLisle wrote:
>> In order to try meet a release date, I would like to use the process as 
>> documented here:
>> 
>> http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1
>> 
>> Synopsis:
>> 
>> June 4th:
>>     * send 2 day warning mail, ask if anyone needs to block the release.
>>     * branch stable-4.1.x to allow 4.2 development to continue.
>> 
>> June 6th:
>>     * build staged release.
>>     * send out call for testing.
>>     * do release on jira with release post-dated to the 11th.
>> 
>> June 11th:
>>     * release from staging.
>>     * publish release.
>> 
>> 
>> I know this is a tight schedule but realistically we need 2 days for 
>> warning/stabilization
>> and 2 (working) days for testing.
>> 
>> WDYT?

ok for me. What's important is that Marius and Thomas can finish what they have 
planned for the EM in time.

>> 
>> Caleb
> 
> Sounds good. I guess that since we're using a proper staging, the RC could 
> actually be the final 4.1 version.

Almost indeed. ATM we have no way to promote an RC into a final so we'll still 
need to rebuild with the "4.1" version but without source code changes.

Thanks
-Vincent

_______________________________________________
devs mailing list
[email protected]
http://lists.xwiki.org/mailman/listinfo/devs

Reply via email to