Hi Joe:


>   What should be the duration for the production line continuity test?  How 
> did
>   you arrive at that duration?  Please include what standard you are using 
> and any
>   specific references.

According to EN 50116, sub-clause 5.1:

    "The test shall be carried out... for 
    the time required to obtain a meaningful 
    reading..."

EN50116 applies to Information Technology 
Equipment, EN 60950

Under EN 50116, the test is done with a 
high-current source, so that the reading 
may change until temperature stability is 
achieved.


Best regards,
Rich






-------------------------------------------
This message is from the IEEE EMC Society Product Safety
Technical Committee emc-pstc discussion list.

To cancel your subscription, send mail to:
     [email protected]
with the single line:
     unsubscribe emc-pstc

For help, send mail to the list administrators:
     Jim Bacher:              [email protected]
     Michael Garretson:        [email protected]

For policy questions, send mail to:
     Richard Nute:           [email protected]

Reply via email to