Hello All,

I have a product in which the customers can envision the user to use a signal
cable longer than 30m.  He has no control over what is used and the product
will function with a cable of that length.  The standard I am testing to is EN
61000-6-2.

 

The requirement for signal lines says the surge on I/O lines must be performed
>from line to earth at 1kV.  Silly question I suppose, but what is meant by
line and what is meant by earth?  I suppose line is the signal line and earth
is protective earth.  Also, I assume the surge must be induced by an inductive
clamp.  My question is how is the surge applied between the signal line and
earth when using a clamp?   

 

Kind Regards, 

 

Sam Wismer 
Engineering Manager 
ACS, Inc. 
*Tel: (770) 831-8048 
*Fax: (770) 831-8598 
*Web: www.acstestlab.com 
 <mailto:*[email protected]> *[email protected] 

 


Reply via email to