On Tue, 4 Aug 2015 14:27:21 +0200 Stefan Schmidt <[email protected]> said:

i'm happy with this cycle - keep going. :)

> Hello.
> 
> After the release is before the release.
> I honestly forgot about posting thsi earlier but given that we have a 
> fixed schedule there should not be much trouble.
> 
> Foloowing the change from last time we have this fixed dates:
> First Monday in October: freeze starts
> First Monday in November: release
> 
> This translates to the following detailed schedule:
> 
> 2015-08-04 Merge window for 1.16 opens
> 2015-09-21 Notice about soon ending merge window
> 2015-10-05 Merge window is over.
>     * Only bug fixes from this point
>     * Alpha release tarball
>     * Four weeks stabilization phase starts
> 2015-10-12 Beta1 release tarball
>     * Only critical fixes from this point
> 2015-10-19 Beta2 release tarball
> 2015-10-26 Beta3 release tarball
> 2015-11-02 EFL 1.16 is out (First Monday in November)
> 
> I'm going to put this in the wiki in a minute.
> https://phab.enlightenment.org/w/efl_and_elementary_1_16/
> 
> Let me know if you have doubts. If I hear nothing in a week I consider 
> this fixed.
> 
> regards
> Stefan Schmidt
> 
> ------------------------------------------------------------------------------
> _______________________________________________
> enlightenment-devel mailing list
> [email protected]
> https://lists.sourceforge.net/lists/listinfo/enlightenment-devel
> 


-- 
------------- Codito, ergo sum - "I code, therefore I am" --------------
The Rasterman (Carsten Haitzler)    [email protected]


------------------------------------------------------------------------------
_______________________________________________
enlightenment-devel mailing list
[email protected]
https://lists.sourceforge.net/lists/listinfo/enlightenment-devel

Reply via email to