Hi,

On Fri, Jul 14, 2017 at 3:51 AM, Andrew Williams <a...@andywilliams.me> wrote:
> Reading down the interfaces task I see that it is expanding faster than we
> can complete the tasks and our deadline looms ever closer.
> https://phab.enlightenment.org/T5301
>
> I propose that we split the list in 2 - the remaining todo items *required*
> to create a stable replacement api - and another for the list of things we
> would like to add once that has happened.
>
> As a somewhat outside observer we are (as is our way) seeing a chance to
> change everything and that's getting in the way of delivering incrementally
> on what we want to achieve.
>
> Are there any objections to me opening an EFL interfaces "part 2" ticket
> and retitling the current one as Te required tasks before finalising?

I have used so far the priority feature of phab to try to implement
that. You can see it at a glance by looking at icon in front of the
task, red is mostly what needs to be absolutely done. Seems it isn't
very visible or usable.

Anyway, you, and anyone else, is welcome to discuss the prioritization
of all this task. As far I have done it following my feeling and got
no feedback on it, yet.
-- 
Cedric BAIL

------------------------------------------------------------------------------
Check out the vibrant tech community on one of the world's most
engaging tech sites, Slashdot.org! http://sdm.link/slashdot
_______________________________________________
enlightenment-devel mailing list
enlightenment-devel@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/enlightenment-devel

Reply via email to