Months? I don't think you did it right.

All told it should take perhaps a couple weeks:
1 day planning, making sure everything is prepared
1 day new server HW/OS/SP/HF installation
1 day Exchange installation, PF rehome, System Folders rehome, connector
rehome
1-3 days for mailbox moves assuming large number of users and off-hours
moves
1 week for user profiles to automatically adjust
1 hour to bring down old server and serve beer.

=======================================================
Andy Webb            [EMAIL PROTECTED]      www.swinc.com
Simpler-Webb, Inc.   Austin, TX            512-322-0071
-- Eating XXX Chili at Texas Chili Parlor since 1989 --
======================================================= 


-----Original Message-----
From: Rowell, John (AFIT) [mailto:[EMAIL PROTECTED]]
Sent: Tuesday, March 26, 2002 7:32 AM
To: Exchange Discussions
Subject: RE: Moving Exchange 5.5 to new hardware


While the Ed Crowley Server Move method is very effective, I would not
discount the backup and restore method, where you do the whole move within
one day.  I've used the Ed Crawley Server Move method and it works fine, but
the downside is that it can take months to move the mailboxes, if you have a
lot of them, and if they are big.  As a result, recently I used the server
move method, and had great success, it was finished in one day and was much
cleaner.  I wouldn't say it's that risky, as long as you know how to back
out of it.  There are also two types of move, i) using one-line backup &
restore, ii) using off-line backup & restore, and I found the latter easier.

> -----Original Message-----
> From: Roger Seielstad [mailto:[EMAIL PROTECTED]] 
> Sent: 25 March 2002 18:14
> To: Exchange Discussions
> Subject: RE: Moving Exchange 5.5 to new hardware
> 
> 
> I suggest rebuilding your plan from the ground up.
> 
> Read the FAQ (Link is below) - there is a well developed set 
> of steps to doing it the right way.
> 
> ------------------------------------------------------
> Roger D. Seielstad - MCSE
> Sr. Systems Administrator
> Peregrine Systems
> Atlanta, GA
> 
> 
> > -----Original Message-----
> > From: Sebastian, Didy [mailto:[EMAIL PROTECTED]]
> > Sent: Monday, March 25, 2002 4:21 AM
> > To: Exchange Discussions
> > Subject: Moving Exchange 5.5 to new hardware
> > 
> > 
> > I have to move my existing Exchange 5.5 to new hardware.  I
> > am restoring from an online backup and will basically install 
> > everything from CD - NT4, Service Pack 6, Exchange 5.5, 
> > Exchange Service Pack 3 and then use my Legato backup to 
> > restore the Information Store and Directory Store.
> > 
> > Can anybody offer any advice or pointers on what to watch out for?
> > 
> > Thanks in advance for you help.
> > 
> > Regards,
> > Didy
> > 
> > _________________________________________________________________
> > List posting FAQ:       http://www.swinc.com/resource/exch_faq.htm
> > Archives:               http://www.swynk.com/sitesearch/search.asp
> > To unsubscribe:         mailto:[EMAIL PROTECTED]
> > Exchange List admin:    [EMAIL PROTECTED]
> > 
> 
> _________________________________________________________________
> List posting FAQ:       http://www.swinc.com/resource/exch_faq.htm
> Archives:               http://www.swynk.com/sitesearch/search.asp
> To unsubscribe:         mailto:[EMAIL PROTECTED]
> Exchange List admin:    [EMAIL PROTECTED]
> 


_________________________________________________________________
List posting FAQ:       http://www.swinc.com/resource/exch_faq.htm
Archives:               http://www.swynk.com/sitesearch/search.asp
To unsubscribe:         mailto:[EMAIL PROTECTED]
Exchange List admin:    [EMAIL PROTECTED]

_________________________________________________________________
List posting FAQ:       http://www.swinc.com/resource/exch_faq.htm
Archives:               http://www.swynk.com/sitesearch/search.asp
To unsubscribe:         mailto:[EMAIL PROTECTED]
Exchange List admin:    [EMAIL PROTECTED]

Reply via email to