Hi folks:

Frank Reilly, tmm, pct  7 and chair of the standing committee on public
works asked me to forward his e-mail to this network.  He's not completely
confortable in handling e-mail. and as I am a member of his TM DPW committee
I am forwarding this as a courtesy to him. He also mentioned that he will be
holding a major public hearing in Upper Nevins Hall on Wednesday, March 12th
on key issues for Town Meeting. If you wish to contact him , his e-mail
address is as listed in the cc: box above; his telephone number is (508)
877-0444.

Larry Schmeidler
TMM, Pct 4


----- Original Message -----
From: <[EMAIL PROTECTED]>
To: <[EMAIL PROTECTED]>
Cc: <[EMAIL PROTECTED]>
Sent: Friday, February 28, 2003 1:40 PM
Subject: riverpath wall


> TOWN ALERT
> STOP RIVERPATH AND ITS THE GREAT WALL FROM
> DIVIDING FRAMINGHAM EAST & WEST .
>
> The opening of Riverpath Rd. as a public way would be the greatest
> mistake ever made by the Town since the railroad crossing in downtown
> Framingham.   The left hand turn from Old Conn Path into Riverpath by many
> hundred of cars returning home and the daily trips of school buses and
> delivery
> trucks etc.  This well prove to be a solid wall of traffic from Riverpath
to
> Hamilton
> St. and when joined by Hamilton St. left turners to will back-up all the
way
> to
> Speen St.  and beyond.  If there is NO RIVERPATH there will be NO left
turn
> with its traffic wall.
>
> HISTORY KEEPS REPEATING & REPEATING & REPEATING
> BEWARE OF DEVELOPERS BEARING GIFTS
>
> IT'S TIME FOR FRAMINGHAM TO START LOOKING ALL GIFT HORSES IN
> THEIR MOUTHS & TO TAKE THEIR HANDS OUT OF OUR POCKETS!!!
>
> IT'S TIME TO REVIEW THE HISTORY OF FRAMINGHAM'S AGREEMENTS,
> PARTICUALLY THOSE INVOLVING THE PRESENT TOWN OFFICALS AND THE
> DEVELOPER ON THE PUD.
>
> Unfortunately the bottom line is that very few of the promises and
commitments
> made to Framingham have ever been completely kept and very few of the
> Agreements have ever proven to be enforceable.  With this record it is
> critical
> that In this year of financial crises the following question has to be ---
> Why can't Framingham's make an enforceable Agreement?  It is imperative
> that no Agreements be made until we have an answer to this question.
> Certainly no Agreement should be made or even considered until after the
> voters have spoken on April 1, 2003.
>
> Here are some of the Agreements that come to mind that have cost the Town
of
> Framingham Millions and Millions of dollars:
> The Planning Boards "Shopper Worlds Agreement" a very costly
> mistake by the Planning Board---which includes an incumbent
> running for re-election in April 1 election,
> 9/90 sewer line Agreement one of the biggest rip-off in the history
> of the Town--involving most of the players working on the new PUD
> Agreement--see history of 9/90 Sewer line.
> The Ashland sewer use Agreement 40 years of underpayments
> because the first year of renewal was not taken advantage of --the
> Town Counsel at that time is a member of the present Board of
> Selectmen.
> The Wonder Bread Agreement another lost court case with a
> favorable payment to the out-of-town owner by a majority of the
> present Board of Selectmen.
>
> History 9/90 Sewer Line:
> When the Board of Selectmen proposed Article 41 for the 1998 Annual Town
> Meeting many
> Town meeting members objected to paying for this improvement in view of
the
> many special
> benefits already given to the 9/90 developer National Development of New
> England (NDNE). It
> appeared that Article 41 was in trouble.
>
> On April 14, 1998 the Standing Committee on Public Works SCPW) voted to
move
> indefinite
> postponement of Article 41 and so notified the Board of Selectmen, the
Town
> Manager Russell
> R. Marcoux, the CFO Mark Rees and the Board of Public Works.   Among the
many
> reasons for
> this motion was the lack of information including costs supplied to the
SCPW
> by the
> administration.
>
> Article 41 was placed on the table by vote of town meeting in order to
give
> the Selectmen and
> the Bannon/Bernstein Committee time to workout an Agreement and for a
motion
> under Article
> 41 that guaranteed a maximum cost to the Town for the completed 9/90 sewer
> line, where
> any and all funding required for a completed project would come from and
what
> were the
> financial guarantees.
>
> The SCPW were ask to reconsider their vote on Article 41 by the
> Administration, the SCPW
> agreed if all the easements were now in place and the Administration's
motion
> guaranteed the
> limit of any town costs for the completed project and which specified the
> source of all potential
> project funding.  Based on that understanding a meeting was called by the
> SCPW Chair Dan
> Gittelsohn for May 27,1998 @ 7 P.M. in the balcony of the Memorial
Building,
> just prior to the
> start of the Town meeting session where Article 41 was to be taken up.
>
> The Bannon/Bernstein Committee, Developers & their Counsel, the Board of
> Selectmen, the
> SCPW Vice Chair  and others met at a Selectmen's meeting just prior to the
> start of the special
> town meeting and the taking of Article 41 off the table, at which time the
> Bannon/Bernstein
> Committee, the Developers & their Counsel and the Board of Selectmen,
agreed
> on a motion
> approved by Town Counsel that was guaranteed to meet the request of the
SCPW
> on funding
> and payments.  Further, it was pointed out by the Administration that
while
> the other users
> of the sewer line didn't really need the new line NDNE did and that
therefore
> there was no
> possibility that the Town would pay more than the $80,000.
>
> Presented with the motion that according to Town Counsel met the SCPW
> request, the SCPW
> voted @ its meeting on 5/27/98 to reconsider their voted and then voted to
> support the new
> motion that was made and voted later that evening. The new motion was as
> follows:
>
> 5/27/98 Voted: That Town Meeting transfer from Sewer Retained Earnings
> $80,000 to design
> and/or to construct a sewer extension line to serve the 9/90 crossing site
> and the Framingham
> Industrial Park.  The balance of the costs associated with said project to
> come from a
> combination of a CDAG grant and/or other contributions from outside
companies.
> Note: It was discovered years later that actually the administration had
paid
> for work on this
> sewer line prior to the May 27,98 town meeting, in addition, funds
> appropriated for the
> Hemenway Pumping Station replacement in 1999, were also used, both the
Board
> of Public
> Works and the Standing Committee on Public Works questioned the legality
of
> such payment
> and demanded an explanation.
>
> The following are pertinent excerpts from that 2/15/00 Town Managers
report
> and
> explanation which was left on the back table during a special town meeting
at
> which this
> matter was not a subject and therefore never discussed or voted on by Town
> Meeting, a
> full copy is available.
>
> Excerpt(s) from that 2/15/00 Town Managers report:
> "The overrun at this time is $407,013.91.  Although the size of this
overrun
> is large, it could have
> been much greater"
> "The first $200,000 was paid -----as  per the Computer Associates Tax
> Increment Financing
> agreement--"
>
> Excerpt(s) from that 2/15/00 Town Managers report:
>  "At this time we have encumbered funds in FY 1999 Sewer Department
> maintenance and
> operating line item to pay our portion of the balance.  The Board of
> Selectmen voted to take this
> action, providing the Town Counsel concurred that the expenditure is legal
> from this account.  He
> has indicated that this is a proper action."
>
> Comment(s):
> For the record the requested copy of the Town Counsels written opinion by
> both the
> Board of Public Works and the Standing Committee on Public Works (SCPW)
have
> never
> been received.
>
> Excerpt(s) from that 2/15/00 Town Managers report:
> "The original Town funding for this project amounted to $80,000---under
> Article 41 ----There was
> a sentenced in the motion for that article that said the balance of the
funds
> for this project would
> come from grants or outside contributions.  The Town Counsel has ruled
that
> this line in not
> legally binding."---"
>
> Comment(s):
> For the record the requested copy of the Town Counsels written opinion by
the
> SCPW
> have never been received.
>
> While the SCPW has never received their requested complete accounting on
the
> 9/90
> project, figures that are available show the town paid not the $80,000
> guaranteed
> maximum limit but between $300,000 and $500,000 (note the original budget
was
> only
> $1,952,700).  As a yard stick $500,000 is 5% of the $10,000,000 Sewer
budget.
>  So 5% of
> your bill went to pay for these overruns.  On a annual $500.00 Sewer Bill
> that would be
> $50.00 for the year.
>
> SUMMARY OF PEOPLE/COMMITTES/ BOARDS INVOLVED
> Developer           National Development of New England (NDNE).
> Bannon/Bernstein Committee  Elizabeth Bannon Town meeting member & Susan
> Bernstein
>                 Planning Board
> Town Counsel            Aaron Bikofsky
> Board of Selectmen          Christopher J. Petrini Chairman, Joyce A.
Tolman
> Vice
>                 Chairman, Valerie M. Mulvey Clerk,  John Kahn & Charlie
>                 Sisitsky.
> Town Manager -      Russell R. Marcoux, Town Manager
> CFO                 Mark Rees, CFO
> SCPW            Dan Gittelsohn Chairman, Francis X. Reilly Vice Chairman,
>                 Barbara E, Gray, Charles Taylor,  Elizabeth Valentini,
Brian
>                 Pollack, Peter Hansen, Carol Briggs, Philip R. Ottaviani,
jr.,
>                 Joseph B. Connolly, Andrew Dallamora, Elisabeth J. Stone,
>                 Robert B. DeShaw, Tilio Franchi, Victor A. Ortiz,
Salvatore
>                 Montillo,

Reply via email to