The DoD has tried to use plasma gasification for MSW and it was a miserable 
failure, costing huge input power, high operating expenses including replacing 
carbon electrodes as expensive and frequent, inconsistent performance, never 
achieving the rated output and very unstable operation. The multi-million 
dollar system was scrapped. Others have also made it to the scrap yard.?


We have a small gasification system that can operate on marine waste, MSW/RDF, 
a system for presorting the MSW into a RDF as a single unit, and operate an IC 
engine as an independent unit and or supply thermal power. It is 18 ft. x 8 ft 
and around 8 ft. tall and operates on around 200 pounds/hour and when mixed 
with other materials, can also operate on waste oils such as those that might 
be derived from bilge water. It produces a white/grey ash with some clinker in 
it, with very low carbon content and volumetric reduction of 90%+.?


To those who are considering developing this type of system, any existing 
process used in gasification should be discarded to avoid wasting a huge amount 
of time and resources without success. This comes after many decades of seeking 
innovative methods to address the problems. The list of what doesn't work is 
quite extensive.?
Sincerely,
Leland T. "Tom" Taylor
Thermogenics Inc.?
www.thermogenics.com
505-463-8422



-----Original Message-----
From: Sunil K Rawal <[email protected]>
To: Discussion of biomass pyrolysis and gasification 
<[email protected]>
Sent: Thu, Mar 27, 2014 3:39 am
Subject: Re: [Gasification] Marine Wastes

  plasma gasification is only best solution and i have experience as project 
incharge of such plant to despose of the industrial hazardous waste and 
generate power.
  
 we can provide you consultancy? for this project
 Sunil Rawal
 Achintya Projects &Services
 Mumbai
 9967064472
 On 27 Mar 2014 01:07, "Gerald Kutney" <[email protected]> wrote: Is 
anyone aware of the use of gasification (or pyrolysis) to treat solid marine 
wastes from ships and vessels; either at the vessels or at the ports.? If not, 
I plan to look at treating MSW as a proxy.? Any comments or ideas?
 ?
?
Gerald Kutney, Ph.D.
Managing Director
Sixth Element Sustainable Management
 Executive Management Consultants for Start-ups
www.6esm.com
?
 


_______________________________________________
 Gasification mailing list
 
 to Send a Message to the list, use the email address
 [email protected]
 
 to UNSUBSCRIBE or Change your List Settings use the web page
 
http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenergylists.org
 
 for more Gasifiers, ?News and Information see our web site:
 http://gasifiers.bioenergylists.org/
 

  
    _______________________________________________ Gasification mailing list  
to Send a Message to the list, use the email address 
[email protected]  to UNSUBSCRIBE or Change your List Settings 
use the web page 
http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenergylists.org
  for more Gasifiers,  News and Information see our web site: 
http://gasifiers.bioenergylists.org/  
  

_______________________________________________
Gasification mailing list

to Send a Message to the list, use the email address
[email protected]

to UNSUBSCRIBE or Change your List Settings use the web page
http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenergylists.org

for more Gasifiers,  News and Information see our web site:
http://gasifiers.bioenergylists.org/

Reply via email to