Dear lakk,

GridWay already does that.
See "Failure Rate Policy (FR)" at
http://www.gridway.org/doku.php?id=documentation:release_5.6:cg#resource_prioritization_policies.

Regards,

Eduardo Huedo Cuesta
http://dsa-research.org/ehuedo



2010/9/11 lak jak <[email protected]>:
> Hi all,
>
> Whenever i submit jobs via gridway metascheduler (i.e), when a job is
> allocated and submitted to a resource, i want to increment the no of job
> allocations made on that resiource.
> If on the other hand, resource faile (i.e) if i dont get a response from the
> resource within some time, then i want to increment the fault index of the
> resource.
>
> I want to use this information when scheduling by gridway  occurs (i.e), i
> want to submit my job to a resource, with low fault index.
>
> How can establish this??
> Can i maintain a table, wherein i store this information?? If so, where
> should this table be maintained? should i have to store this information in
> the GIS and retrieve it when i do the scheduling process?
>
> Please help me by giving out some  ideas.
>
> Thanks in advance,
> lakk
>
>
>