Generally, applications waits for the ABARS to complete before continuing 
to process which still puts the backup in the critical path.



Yes, it would be but it is not what the OP asked for.

-----Original Message-----
From: Gibney, Dave [mailto:[email protected]] 
Sent: Tuesday, September 17, 2013 1:55 PM
To: [email protected]
Subject: Re: HMIGRATE in parallel

Is this not called ABARS?

> -----Original Message-----
> From: IBM Mainframe Discussion List [mailto:[email protected]] 
> On Behalf Of Darth Keller
> Sent: Tuesday, September 17, 2013 8:54 AM
> To: [email protected]
> Subject: Re: HMIGRATE in parallel
> 
> Interesting approach -
> 
> If the poster is actually trying to get an application PIT (point in 
> time) backup of his application using HSM, the only way I could get 
> that to work here would be to flashcopy the whole thing to new names & 
> then run HSM backups against those new names.  Then it would no longer 
> matter that HSM single- threads everything and it would also take the 
> entire backup process outside the critical path.
> 
> Now I've only been watching this thread with 1 eye,  So if I missed 