Richard, 
SFS takes an automatic control data backup whenever the log disks reach
80% full.  You can also initiate one manually with the FILEPOOL CONTROL
BACKUP command.  Make sure your log disks are large enough to prevent
unscheduled backups, and then schedule a FILEPOOL CONTROL BACKUP for a
time when your users aren't testing.
 

 
Dennis                      
 

"History is not a school-mistress. She does not teach. She is a prison
matron who punishes for unlearned lessons."  -- Vasily Klyutchevsky,
Russian historian


-----Original Message-----
From: The IBM z/VM Operating System [mailto:[EMAIL PROTECTED] On
Behalf Of Schuh, Richard
Sent: Wednesday, June 14, 2006 12:40
To: [email protected]
Subject: [IBMVM] SFS Control Data Backupsi

We have a group of users, running critical tests, that experienced
erratic response during a period when SFS was taking a Control Data
Backup and LUWs were suspended. These users all access the same
directory R/O. The directory is DIRC. The question is, will assigning
this directory to a dataspace have a positive effect on the response
times, or will a Control data Backup still interfere (assuming that the
LUW suspension was the problem)? If that is not likely to help, is there
any way to prevent LUW suspension during these critical tests? I am
already considering the possibility of creating a new filepool for this
one application, but am not looking forward to doing so with any great
amount of anticipation.

Regards,
Richard Schuh

Reply via email to