Russia
-Prime Minister Vladimir Putin visits centralcontrol unit at System Operator
of Unified Energy System (SO UES)

Transcript of the meeting:

 

A. Novikov (Main Control Center
duty operator): Mr Putin, please allow me to present my report.

 

Operational mode is normal; the frequency is maintained
within 50, plus or minus 0.05, Hertz. Power flows in, the monitored transfer is
within permitted values. Voltage on the test points does not exceed maximum
operating values. Nuclear, thermal and hydro power station workloads are on
schedule. No maintenance operations are planned at this time.

 

The expected peak load in the Unified
Energy System of Russia is expected to be 135,000 MW
without the Far Eastern System Operator, with an expected 500 MW
reserve. The Siberian System Operator has already passed the peak
load of 30,200 MW of consumption. There were reserves of one thousand MW at the
Siberian SO.

 

Fuel reserves at SO power stations are generally within
the prescribed values, but there is a hang-up at the Vladivostok Steam Power
Plant. They have a six day fuel supply and had one power outage, but that
transmission line is back in service. It's being used for re-routing.

 

Report complete.

 

Vladimir Putin: Okay.

 

You know that currently global warming is being discussed
internationally. We have extremely low temperatures, especially in Siberia, 10 
degrees lower than normal, with the average
temperature at minus 29. And in December, as you reported (addressing S.
Shmatko) electric power consumption in Russia was at its highest
since 1990.

 

The first question is how are we doing with this winter
peak load? Second, concerning the accident at the transmission line in the 
Maritime Territory: how are repairs proceeding?
Third are the problems connected with the Sayano-Shushenskaya Power Plant's
terminated capacity. We have agreed on power redistribution especially during
the fall and winter period. How are things with that?

 

And the next question, also related to the
Sayano-Shushenskaya Power Plant being out of service, is that of smoothing
price hikes. We have agreed and the Government decreed that price changes would
be leveled. How is this being handled? How is the government's decree being
implemented?

 

Nikolay Shulginov (SO UES first deputy chairman): We
experienced abnormally low temperatures in December, and the situation was
satisfactory. The point is, the Energy Ministry, when preparing for the winter,
was using a scenario with much lower temperatures than the climatic average,
abnormal temperatures. That is why in all the territories, and in the UES in
general, those temperatures were used for load calculations, and the same
method was used to estimate fuel reserves.

 

Also, maintenance operations were scheduled using the
same scenario, and during the peak load period there is an absolute minimum of
such operations, only short repairs, mostly on weekends and holidays.

 

All that allowed us to get past the peak load period and
the record high numbers you mentioned. And those record highs were also in the
regions, not only in the UES. The Moscow Power System also showed a
consumption maximum of 17,230 MW which is an absolute record and historical
maximum.

 

Preparations for the winter emphasised maintenance. The
Energy Ministry conducted special activities and set up a task force to monitor
maintenance and repairs. So all repair work, in Siberia
in particular, was under control. As for Siberia,
the peak was between 1500 and 1600 hours, and now the peak stands at 29,632 MW.
It is the current peak, and fairly substantial. The temperature there, as we
know, stands at 30 degrees below, and in the Trans-Baikal area - down to minus
40 degrees.

 

What are our power flow reserves? 500 kV line power flow
from Kaaklhstan to Siberia totaling 623 MW
with a permitted value of 1,800 MW. That is, here we have a reserve of
approximately one thousand MW.

 

Also, as the operator has reported, thermal stations have
rotating and cold reserves. The equipment is currently standing in reserve
because we have working days coming and peak consumption will go up. That
equipment will be put into operation at the end of the holiday season.

 

What else is there concerning Siberia
and the Sayano-Shushenskaya Power Plant being decommissioned? We have a plan,
approved by the Energy Ministry. It involves the whole range of operations and
it expedites the processes to eliminate accidents.

 

The plan also includes capacity increases at Siberian
thermal power stations. Increased fuel reserves were specified here, and
specific activities include 220kV transmission line construction. You can't see
them on this chart as it only shows over-500 MW networks. Plans also include
installing capacitor banks at the Oznachennoye and Aluminievoye substations to
maintain the required voltage at continuous operating cycle enterprises. The
Federal Network Company has more details on how some of those activities have
been completed.

 

Additionally, a number of training exorcises have been
conducted. Single line shutdown emergency scenarios have been devised. All this
is aimed at coping with peak loads including December's and during this cold
spell, plus the forecasted consumption of the upcoming working days. We can say
that fall-winter peak loads in Siberia will be
dealt with in an efficient manner.

 

Sergei Shmatko (Russian Energy Minister): I would
like to note again, that December 16th was an all-time record peak in
Khakassia. That is, Khakassia consumed a maximum amount of power on that day
and even though the Sayano-Shushenskaya Power Station was inoperable,
everything was okay.

 

Vladimir Putin: And how was power distribution
organised after the Sayano-Shushenskaya Power Plant was shut down?

 

Sergei Shmatko: Power is supplied from the European
regions via Kazakhstan,
as Nikolai Shulginov showed, in the amount of about 600 MW. In December we had
up to 1,700 MW transferred from the European regions to Western
 Siberia, and also about 230 MW from Tomsk Region. We also have
reserves we haven't used - it is the power distribution from Irkutsk Region to 
Western Siberia.

 

Vladimir Putin: Are they considered a backup?

 

Sergei Shmatko: Yes, absolutely

 

Nikolay Shulginov: We have access to capacity which is
being transmitted, depending on transmission line capacity, to the western part
where we had the accident.

 

Sergei Shmatko: In other words, due to the unavailability
of the Sayano-Shushenskaya Power Plant, we have a small shortage of power
generating capacity with the Siberian SO, but because of the power
redistribution we are confident that power supplies to the territories will be
uninterrupted.

 

Vladimir Putin: Well, how about price hike
smoothing?

 

Sergei Shmatko: Following your instructions to curb
speculation due to a generating shortage, primarily due to the
Sayano-Shushenskaya Power Plant problem, the government issued a decree and a
corresponding price-leveling mechanism has been developed.

 

I would like to report that in late December due to low
temperatures in the European areas of the country, the wholesale price rose
from 600 to 1,000 rubles. In view of this, a price-leveling mechanism was
designed and approved. As a consequence, the price dropped back down to 600
rubles.

 

This shows that we have tested the mechanism. There was a
small increase on January 1, but for different reasons.

 

Vladimir Putin: I would like to know what is going
on in the Far East because of the transmission line failure and in the North 
Caucasus because of the snowfall?

 

Sergei Shmatko: Oleg Budargin, Federal Network Company
CEO, will report on the transmission line accident in Primorsk

 

Oleg Budargin (FNC UES CEO): At 14:37 hours Moscow time, high-voltage
transmission line 500 of the Primorskaya Steam Power Plant, far eastern
substation 500, failed.

 

Vladimir Putin: The substation failed?

 

Oleg Budargin: The power station mainline and the
substation. The location of the problem has been identified 600 km from the
power plant, and repair crews have been sent there. We hope to fix it within
six to eight hours. No consumers have experienced a power failure. The effect
was insignificant: when the power plant safety system snapped, two
power generating units were stopped, units three and five. This cross-switch
caused a short interruption. Within one hour power supplies were restored to
all consumers.

 

Vladimir Putin: What about the North
 Caucasus?

 

Sergei Shmatko: Nikilai Shvets reports.

 

Nikolay Shvets (MRSK Holding CEO): Conditions in the North Caucasus are really 
tough. High winds, snow
accumulation on power lines, icing, trees falling.

 

This morning 4000 consumers lost power in a Dagestan district. And the capacity 
is 1.5MW. Eighteen
support towers have been downed, and new supports are now being erected.

 

Vladimir Putin: Eighteen supports?

 

Nikolay Shvets: Yes, 18 wooden supports. The situation is
complicated by mountainous terrain, and the roads are blocked by snow. A
helicopter is being used to solve the problem.

 

There was a threat to normal operations.

 

Vladimir Putin: One second, when are you going to
fix that problem?

 

Nikolay Shvets: By noon tomorrow.

 

Vladimir Putin: By noon tomorrow?

 

Nikolay Shvets: Exactly.

 

Vladimir Putin: Okay.

 

Nikolay Shvets: Later today 50% of the population will be
reconnected. About two thousand people will remain without power, basically
villages high in the mountains. They have stove heating; socially significant
facilities are absent.

 

Vladimir Putin: Everything is socially significant
where people live. Okay. Did you mean to add something?

 

Nikolay Shvets: Regular power supplies to Cheget and
Terskol mountain resorts were threatened.

 

Vladimir Putin: Near Elbrus?

 

Nikolay Shvets: Yes. Avalanches are a threat there, and
one of the transmission lines was covered by an avalanche.
The system short circuited through the snow to the ground. Power was
cut every 10-15 minutes in the reconnection process. However, the line was
fully operable about an hour ago, although the risk of failure remains. The
situation is aggravated by the Civil Defense Ministry closing the area to our
crews. When the ban is lifted, we will work overtime to ensure uninterrupted
service to the Elbrus area.

 

Vladimir Putin: The crews are not allowed in due to
avalanche danger?

 

Nikolay Shvets: Right. And there was a blackout in the
Dombai mountain ski resort area. There was another transmission line disruption
and power was cut off. The cause is now being investigated. I think the failure
is to be fixed shortly.

 

Vladimir Putin: When exactly?

 

Nikolay Shvets: I believe within two hours.

 

Vladimir Putin: Within two hours?

(Addressing Shmatko) As to the scope of regions' and
municipalities' responsibility, it is evident that you will not be able to see
and direct everything from the ministry, from Moscow. Maintaining contact 
you're your
colleagues is essential - both at the regional and municipal levels to prevent
such glitches as the one in a Chita
garrison.

 

Sergei Shmatko: Following your directive, a Federal Power
Supplies Safety Task Force was organised. And regional safety task force heads
are members.

 

I should say these task forces had been set up in all of Russia's
regions by the fall-winter period. We constantly keep in contact. You are
right; there is a gap where the "big authority" contacts the
municipalities. The heads of the network units have been instructed to render
the necessary assistance.

 

Vladimir Putin: The key issue is that the "big
authority" should work faultlessly because we cannot allow unpredicted
situations. The response should be prompt and effective.

 
http://ap2i.blogspot.com/

--- On Sun, 1/24/10, CHPStar <[email protected]> wrote:

From: CHPStar <[email protected]>
Subject: 500 kV control systems
To: [email protected]
Cc: [email protected], [email protected], [email protected]
Date: Sunday, January 24, 2010, 10:57 PM

ABB sets transmission
 record with project in ChinaElectric Light & Power - ‎Jan 11, 2010‎This would 
enable power supply for an additional 1 million people in China every year as 
compared with the 500 kV HVDC systems in use there. ...Russia - Prime Minister 
Vladimir Putin visits central control unit at System ...ISRIA - ‎Jan 5, 
2010‎500 kV line power flow from Kaaklhstan to Siberia totaling 623 MW with a 
permitted value of 1800 MW. That is, here we have a reserve of approximately 
one ...Alberta's Electricity Transmission Debate – An Update On Bill 50Mondaq 
News Alerts (registration) - Conor T. Chell - ‎Jan 7, 2010‎The Alberta 
Independent Electric System Operator (AESO) had previously identified the 
immediate requirement for five critical infrastructure projects. ...
http://ap2i.blogspot.com/


      


      

Kirim email ke