Alberta's Electricity Transmission Debate - An Update On
Bill 50.

 

On November 25, 2009, Bill 50, the Electric
Statutes Amendment Act, 2009, was passed (as amended) by the Alberta
Legislature. The bill amends three existing pieces of legislation:
the Alberta Utilities Commission Act, the Electric Utilities Act and the Hydro
and Electric Energy Act.

With the passing of Bill 50, the need
identification process is eliminated for
"critical transmission infrastructure" as designated by the
Lieutenant Governor in Council, or as set out in a schedule to the Electric
Utilities Act (the schedule having been added as a result of the amendments
created byBill 50). The Lieutenant Governor in Council can now designate
"critical transmission infrastructure" if the
infrastructure is:

An intertie;

To serve areas of renewable energy;

A double circuit transmission facility that is
designed to be energized at a nominal voltage of 240,000 volts;

Designed to be energized at a voltage in excess of
240,000 volts; or

Critical to ensure the safe, reliable and economic
operation of the interconnected system, in the opinion of the Lieutenant
Governor in Council.

The Alberta government, rather than the Alberta Utilities
Commission (AUC), now becomes the responsible authority for determining whether
certain transmission infrastructure projects are needed in Alberta.
As a result of Bill 50, a series of major
electrical transmission projects deemed as "critical
infrastructure" are exempted from the normal regulatory and cost
assessment process previously undertaken by the AUC. Essentially, the
provincial cabinet is provided with more control over which power lines are
built and when, but the AUC retains control over where they are to be built.

The Alberta Independent Electric System Operator (AESO)
had previously identified the immediate requirement for five critical
infrastructure projects. The first project, a southern system reinforcement
intended to open the grid to more wind power, was approved by the AUC on
September 8, 2009, with a cost estimated at $2.5 billion by the Alberta
government. With the implementation of Bill 50, four additional
proposed infrastructure projects will be constructed, including (associated
costs estimated by the provincial government in brackets):

Two high-voltage direct current lines between Edmonton
and Calgary, to provide power to consumers in central and southern Alberta
($3.1 billion);

One alternating current line between Edmonton
and Alberta'sIndustrial Heartland, to provide power to industrial
consumers (e.g. upgrading facilities) ($400 million);

Two alternating current lines between Edmonton and Fort
McMurray to carry power from co-generation plants to consumers ($2 billion);

A substation in Calgary to provide more reliable service
to customers in south Calgary ($100 million).

The total cost for the five projects identified by the
AESO was estimated by the provincial government at $8.1 billion, but critics
of Bill 50 had suggested that significantly higher costs will be
involved, in the range of $14-20 billion.

In passing Bill 50, the government argued that
majortransmission projects are akin to roads and hospitals, and should not
require public input if the project is critical to the province. In support of
the bill, Energy Minister Mel Knight indicated that the current
power transmission system is inefficient, as it has not been upgraded
in more than 20 years, resulting in approximately $220 million worth
of electricitybeing lost in 2008, enough to power approximately 350,000
homes. The government also argued that the current system is congested and
limits the connection of new generation sources. Proponents were fearful that
the power line system in Alberta has not kept pace with the province's growing
population, creating the potential for widespread electricityshortages.
Additionally, some suggested that an increase intransmission capacity
would prevent consumers from being stranded without power and
more transmission lines would create competition in
the electricity market, giving consumers more choice.

Critics of Bill 50 disagreed with the
notion that an increase intransmission would increase competition in the
market, arguing that deregulation of the electricity industry in
Alberta was intended to achieve this purpose. These parties also expressed
concerns regarding transparency and that public consultation was to be removed
from the needs assessment process. Critics maintained that if the AUC were
involved in the determination of need, a more thorough analysis
ofelectricity system capacity and cost issues would occur. Some accused
the government of proposing Bill 50 with the ulterior motive of
ultimately exporting electricity to the energy-hungry U.S. An
increase in transmission would entrenchAlberta's reliance on
coal-fired electricity, some said. Natural gas-fired power plants and an
increase in generation facilities closer to electric consumption points were
identified as possible alternatives to the bill.

Bill 50 has potential implications for several
of the players inAlberta's electricity market. Prior to the passing
of the bill, ATCO Electric and Altalink had been approved by the
government to begin preliminary design plans and environmental and
site-location assessments with respect to the power lines between Calgary and
Edmonton, while EPCOR and Altalink had begun similar work with respect to the
lines between Edmonton and the Industrial Heartland. Enmax Corporation has
been, and continues to be, the most vocal in its opposition
of Bill 50, preferring the establishment
of electricity generation closer to where it is ultimately used, with
plans to build three facilities that would add over 1,000 MW of power to
Calgary and surrounding areas.

On November 24, 2009, the Alberta government
amended Bill50 with amendments focusing on public interest, access to
costs information and staging. The amendments clarified that the AUC must
consider the public interest in the decisions it makes on the siting of
critical transmission infrastructure and provided for the
establishment of an oversight committee, including members from the AESO and
customer representatives, intended to give consumers regular and timely access
to project information, including project cost, scope and timelines.
Additionally, amendments provided for the staging of the Edmonton to Calgary
project and the Edmonton to Fort McMurray project, which, according to the
government, is expected to defer approximately $2 billion in expenditures.

Although passed on November 25, 2009, it is not clear
thatBill 50 will be the last word on
the transmission infrastructuredebate in Alberta. On November
19, 2009, a Notice of Complaint (Application No. 1605627, Proceeding ID No.
398) was issued by the AUC respecting a claim by the Lavesta Area Group that
the AESO has breached section 34(1) of the Electric Utilities Act. The Lavesta
claim alleges that the AESO has not filed a valid needs identification document
(NID) in association with its determination that the proposed expansion
of Alberta's transmission system is required to meet the needs
of Alberta. The Lavesta Area Group claims that the AESO is relying on a NID
that is invalid as a result of the November 2007 Alberta Court of Appeal
Decision in Lavesta Area Group and Alberta (Energy and Utilities Board) 2007
ABCA 365, which dealt with the highly publicized controversy respecting the
proposed 500 KV transmission facilities between Calgary and Edmonton.
It is unclear what impact the AUC's determination on the Lavesta claim will
have on thetransmission infrastructure debate in Alberta,
however interveners have now registered with the AUC and a formal proceeding is
underway.

Since the passing of Bill 50, chief executive
officer of Enmax, Gary Holden, has publicly denounced the Alberta government
with accusations that during information sessions held prior to the passing
of Bill 50 the government agreed to allow power companies to build
certain projects regardless of need or regulatory requirements. Enmax's
allegations have caused outgoing auditor general Fred Dunn to comment that an
investigation is warranted into whether the government colluded with power
companies respecting the construction of the
various transmission projects proposed by Bill 50. The
claims have also led to a request for Ethics Commissioner Neil Wilkinson, who
is normally limited to probing the actions of members of the legislative
assembly, to examine the matter.

Whatever the outcome of the various processes that are
occurring following the passage of Bill 50, it is clear that
thedebate regarding the construction of
critical transmissioninfrastructure in Alberta has yet to be resolved.

The content of this article is intended to provide a
general guide to the subject matter. Specialist advice should be sought about
your specific circumstances.

Mr Conor Chell

Bennett Jones LLP

4500 Bankers Hall East

855 - 2nd Street S.W.

Calgary

Alberta

T2P 4K7

CANADA

Tel: 4032983650

Fax: 4032657219

E-mail: [email protected]
http://ap2i.blogspot.com/

--- On Sun, 1/24/10, CHPStar <[email protected]> wrote:

From: CHPStar <[email protected]>
Subject: 500 kV control systems
To: [email protected]
Cc: [email protected], [email protected], [email protected]
Date: Sunday, January 24, 2010, 10:57 PM

ABB sets transmission
 record with project in ChinaElectric Light & Power - ‎Jan 11, 2010‎This would 
enable power supply for an additional 1 million people in China every year as 
compared with the 500 kV HVDC systems in use there. ...Russia - Prime Minister 
Vladimir Putin visits central control unit at System ...ISRIA - ‎Jan 5, 
2010‎500 kV line power flow from Kaaklhstan to Siberia totaling 623 MW with a 
permitted value of 1800 MW. That is, here we have a reserve of approximately 
one ...Alberta's Electricity Transmission Debate – An Update On Bill 50Mondaq 
News Alerts (registration) - Conor T. Chell - ‎Jan 7, 2010‎The Alberta 
Independent Electric System Operator (AESO) had previously identified the 
immediate requirement for five critical infrastructure projects. ...
http://ap2i.blogspot.com/


      


      

Kirim email ke