Hi Stephane,


What happens if a feature is not ready by the Major (feature driven) release 
date? Is the feature de-scoped from the spec (so compliance is still achieved) 
or is the date release pushed out (until feature compliance is achieved) or ??

? [June] Basically, ?feature driven? means pushing out the release date until 
the feature compliance is achieved.

? Nevertheless, this decision can a little bit depend on the situation. If that 
feature is important, we cannot help pushing out the release.

? But if the feature is minor and the spec can be changed, then we will try , 
but I think changing the spec is not easy in general at the last minute.



June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



From: Stephane Lejeune (stlejeun) [mailto:[email protected]] 
Sent: Tuesday, May 19, 2015 8:53 PM
To: ???(June Yong Young); 'Lankswert, Patrick'; 'Agrawal, Sachin'; iotivity-dev 
at lists.iotivity.org; '???'; '???'
Subject: RE: [dev] 0.9.1 release schedule



Hi June,

Thank you for sharing these details ahead of the ISG meeting minutes 
publication.

Could I ask for one clarification though:

TIA, What happens if a feature is not ready by the Major (feature driven) 
release date? Is the feature de-scoped from the spec (so compliance is still 
achieved) or is the date release pushed out (until feature compliance is 
achieved) or ??



  Stephane.



P.S. If this will be clarified in the ISG meeting minutes, I can wait until 
their publication?





From: iotivity-dev-bounces at lists.iotivity.org 
[mailto:[email protected]] On Behalf Of ???(June Yong 
Young)
Sent: Tuesday, 19 May, 2015 2:19 AM
To: 'Lankswert, Patrick'; 'Agrawal, Sachin'; iotivity-dev at 
lists.iotivity.org; '???'; '???'
Subject: Re: [dev] 0.9.1 release schedule



Hi Pat,



June 5th release was changed to end of May release in the ISG meeting last week.

It was because there are some OIC member companies to want May release ASAP.



The following is the meeting minute that Deniel captured.





Release process discussion/owners: June and Pat (filling in for George)

-release types:  lightweight, agile-style releases and major releases

-release criteria for each release type, including go/no-go decision process

-quality criteria for each release type

-process for each type (branch vs tag, expected collateral, announcement)

(Resolution) 

1)    Release Schedule


May

Minor Release

Spec-A mandatory features(Pre Release)


June

Plugfest




July

Minor Release

Spec-A compliant feature + Spec-B(partially)


August

Plugfest




October

Major

Spec-A/B compliant feature




Minor

Every two month


April

October

Major

Twice a year









And the following is what I announced in the IoTivity session in OSWG meeting.



cid:image001.png at 01D09156.D18120A0





June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



From: Lankswert, Patrick [mailto:[email protected]] 
Sent: Monday, May 18, 2015 11:39 PM
To: juney at samsung.com; Agrawal, Sachin; iotivity-dev at lists.iotivity.org; 
???; ???
Subject: RE: [dev] 0.9.1 release schedule



June,



The original dates from the ISG meeting were EoMay (May 29th) for feature 
complete and June 5th for code freeze. Why has this been changed?



Pat



From: JuneYong Young [mailto:[email protected]] 
Sent: Monday, May 18, 2015 2:21 AM
To: ???; Agrawal, Sachin; Lankswert, Patrick; iotivity-dev at 
lists.iotivity.org; ???; ???
Subject: Re: [dev] 0.9.1 release schedule



To all,



I've slightly revised some items below after discussion with Samsung QA.



- 0.9.1 : ?Spec vA Mandatory features?

- Schedule

  . 5/20, Feature complete & Review Complete and make "0.9.1-RC1" release to QA

  . 5/25, QA reports back.

  . 5/26, "0.9.2-RC2" release just in case there an issue occurs on basic 
functionality

  . 5/28, QA to run Sanity check (about only the issue items)

  . 5/29, Website Open 

- Mandatory items must be completed

  . Any basic functionality should be working

  . Merge CA(connectivity Abstraction) branch onto one master branch

- The items strongly requested, but no gating issues to release

  . BT/BLE Support, Noti. Manager, Android API

  . If any issues related to these items, they will be described as known 
issues.

- QA

  . P1 problems to be fixed.

 If it is not fixed, then it has to be lowered down to P2 after discussion with 
QA.



To Pat,

George is a release manangement function counter part of Intel side.

Please check with Intel QA since George is not present now.





Regards

June



June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center,  IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



------- Original Message -------

Sender : ???<juney at samsung.com> S6(??)/??/IoT Solution Lab(S/W??)/????

Date : 2015-05-15 11:40 (GMT+09:00)

Title : [dev] 0.9.1 release schedule



To all,



According to the discussion result in the last ISG & OSWG F2F meeting,

we will release & open 0.9.1 at the end of May with schedule driven.



So, 0.9.1 will be released based on the following. If any questions or 
concerns, then let us know.



- 0.9.1 : ?Spec vA Mandatory features?

- Schedule

 . 5/22, Feature complete & Review Complete

 . 5/28, exit from QA

 . 5/29, Website Open 

- Mandatory items must be completed

 . Merge CA(connectivity Abstraction) branch onto one master branch

- The items strongly requested, but no gating issues to release

 . BT/BLE Support, Noti. Manager, Android API

- QA

 . P1 problems to be fixed.

If it is not fixed, then it has to be lowered down to P2 after discussion with 
QA.







June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair 

IoTivity Release Function Lead


Samsung Electronics Co.,Ltd.

Software R&D Center, IoT Solution Lab. | Web & Convergence Team

Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107

E-mail :juney at samsung.com



From: iotivity-dev-bounces at lists.iotivity.org 
[mailto:[email protected]] On Behalf Of Agrawal, Sachin
Sent: Friday, May 15, 2015 8:30 AM
To: Lankswert, Patrick; iotivity-dev at lists.iotivity.org
Subject: Re: [dev] Last call for contributions for 0.9.1



Hi Pat,



Can you clarify this statement?

?Failing to do so will result in your contribution being held until the next 
release?



My assumption is that ?master? will still be open for code check-ins, except 
that the check-in?s

after May 28th will NOT be tagged for 0.9.1 release. 

Is that right?



Thanks

Sachin

503-264-8071



From: iotivity-dev-bounces at lists.iotivity.org 
[mailto:[email protected]] On Behalf Of Lankswert, Patrick
Sent: Wednesday, May 13, 2015 2:21 PM
To: iotivity-dev at lists.iotivity.org
Subject: [dev] Last call for contributions for 0.9.1



To all,



The following dates are important for the 0.9.1 release:

June 5th ? Code Freeze

May 28th ? Feature Complete and Review Complete



It is important that contributions be completed by May 28th, so that system 
testing may start. 



If you have a contribution that you want considered for 0.9.1 that is not 
already in gerrit review, you must announce on this list with an estimated date 
for your submission. Failing to do so will result in your contribution being 
held until the next release.



We are working on a more formal release schedule process what will be published 
on the wiki.



Pat



Patrick Lankswert

Discovery and Connectivity (Core Stack) Maintainer




  
<http://ext.samsung.net/mailcheck/SeenTimeChecker?do=c7ba9f2f7185d6393c28b3c940eb11c25a9f8d8a74e3363d87dfe03c47d8dbcb08c5ce1bd480a15cd4a87a1fb2ad96504bea3c1765014a1208cece8541bc14eacf878f9a26ce15a0>
 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150520/d24538b6/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 141688 bytes
Desc: not available
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150520/d24538b6/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.gif
Type: image/gif
Size: 13168 bytes
Desc: not available
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150520/d24538b6/attachment.gif>

Reply via email to