Hi everyone, 2.204.1 is scheduled for Dec 18, .2 would be released on Jan 15, with the RC scheduled for on Jan 1.
I don't expect a lot of backport candidates, or feedback on .1 in general, to come in between Dec 18 and Jan 1. Hence I propose we take a two week break as in past years, postponing the RC and release of .2 (and all subsequent releases) by two weeks, so that the new dates are: - Dec 18: .1 release (unchanged) - Jan 15: .2 RC - Jan 29: .2 release - Feb 12: .3 RC etc. Thoughts? Daniel -- You received this message because you are subscribed to the Google Groups "Jenkins Developers" group. To unsubscribe from this group and stop receiving emails from it, send an email to [email protected]. To view this discussion on the web visit https://groups.google.com/d/msgid/jenkinsci-dev/7D652E56-59DA-4C41-A48A-D05CBA6CCFA0%40beckweb.net.