Hi everyone,

2.204.1 is scheduled for Dec 18, .2 would be released on Jan 15, with the RC 
scheduled for on Jan 1.

I don't expect a lot of backport candidates, or feedback on .1 in general, to 
come in between Dec 18 and Jan 1.

Hence I propose we take a two week break as in past years, postponing the RC 
and release of .2 (and all subsequent releases) by two weeks, so that the new 
dates are:

- Dec 18: .1 release (unchanged)
- Jan 15: .2 RC
- Jan 29: .2 release
- Feb 12: .3 RC
etc.

Thoughts?

Daniel

-- 