+1

On Wed, 11 Nov 2020 at 09:48, Daniel Beck <[email protected]> wrote:

> Hi everyone,
>
> We have an LTS release scheduled for December 30, which probably isn't
> useful: The RC testing period is from Dec 16 to Dec 30. Plus who wants to
> release things the day before NYE?
>
> I propose we add a two-week break between 2.263.1 release and 2.263.2 RC,
> postponing all future RCs and releases by two weeks accordingly.
>
> Before:
> Dec 2 - 2.263.1 Release
> Dec 16 - 2.263.2 RC
> Dec 30 - 2.263.2 Release
> etc.
>
> After:
> Dec 2 - 2.263.1 Release
> Dec 30 - 2.263.2 RC
> Jan 13 - 2.263.2 Release
> etc.
>
> This should give us a useful RC testing period in early January. Since
> this is the .2 release, a slightly longer backporting period in December
> could help getting more fixes in for issues discovered in .1 as well.
>
> While the RC would be scheduled for Dec 30, it could always be prepared
> earlier if nobody would be around in late December to do it. If that
> doesn't work out and it is published in early Jan, that wouldn't be too
> much of a delay either.
>
> WDYT?
>
> Daniel
>
> --
> You received this message because you are subscribed to the Google Groups
> "Jenkins Developers" group.
> To unsubscribe from this group and stop receiving emails from it, send an
> email to [email protected].
> To view this discussion on the web visit
> https://groups.google.com/d/msgid/jenkinsci-dev/821EFEC7-55BA-475B-B977-1DCC1F559B82%40beckweb.net
> .
>


-- 
Antonio Muñiz
Human, Engineer
CloudBees, Inc.

-- 
You received this message because you are subscribed to the Google Groups 
"Jenkins Developers" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To view this discussion on the web visit 
https://groups.google.com/d/msgid/jenkinsci-dev/CAJc7kzSYHzwOJjiGtWsz2Ozav%2Bry3u2%3D4RriszTCc2a-6cCT9Q%40mail.gmail.com.

Reply via email to