https://bugs.freedesktop.org/show_bug.cgi?id=57865
GerardF <[email protected]> changed: What |Removed |Added ---------------------------------------------------------------------------- Status|UNCONFIRMED |RESOLVED Resolution|--- |NOTABUG CC| |[email protected] --- Comment #1 from GerardF <[email protected]> --- (In reply to comment #0) > A8 =DATE(2012,MONTH(A7)+1,25) (25/01/13) which correct, BUT > A9 =DATE(2012,MONTH(A8)+1,25) (25/02/12) which is WRONG > A9 should be (25/02/13) not (25/02/12)! A8 contains 25/01/13 MONTH(A8)=1 MONTH(A8)+1=2 DATE(2012;MONTH(A8)+1;25)=DATE(2012;2;25) Why should result of DATE(2012;2;25) be 25/02/13 ??? -- You are receiving this mail because: You are the assignee for the bug.
_______________________________________________ Libreoffice-bugs mailing list [email protected] http://lists.freedesktop.org/mailman/listinfo/libreoffice-bugs