Hi, I've sketched out a plan for selection a Work Tracking Tool (or tool(s) if necessary).
I've shared the Tool Spreadsheet to start gathering the requirements for the tool using the PM's for input. Plan: Week of May 16th (Week 20): Consider this the start of the Pilots and Evaluations Week of May 23rd (Week 21): Gather PM's input. Get list of Tools being piloted into the spreadsheet (Vicky) Week of May 30th (Week 22): or because of Public Reviews probably Week of June 6th: prioritize the list with the PM group. Socialize requirements with people like Kiko, David R., Joe Bates etc. June 30th (Week 26): End of Pilot and Evaluations Week of July 4th (Week 27): Update spreadsheet with Evaluation feedback. PM's propose a solution for August Gathering Thanks for your input. Regards, Vicky Janicki [email protected] Program Director, Member Services Linaro Tel: +1.978.319.1661 mailto: [email protected] IRC: vicky Skype: vjanicki
_______________________________________________ Mailing list: https://launchpad.net/~linaro-project-management Post to : [email protected] Unsubscribe : https://launchpad.net/~linaro-project-management More help : https://help.launchpad.net/ListHelp

