Hello all,

At the telecon today we will discuss this timeline:

July 15 - Start updates to UML Model, FRS, OCD, sizing spreadsheets for
baseline. 
July 17 - Discuss CPU implications of query workload
July 19 - Need changes in estimates for 1 year construction start slide.
COB Freeze changes to disk/tape estimates, Thomas Frey will lock files in
docushare, update with import information, and import into Primavera and
ProPricer
July 24 - Get copies of estimate sheets from archive for updating CPU costs
July 26 - Freeze changes to CPU cost estimates
July 31 - Add in-kind resources to estimates, freeze.  Align internal and
IPAC estimates.  Complete updates to UML model, FRS, OCD, sizing
spreadsheets.   Tim to close on galactic exclusion zone and # sources
processed/image issues.
August 7 - Final adjustments to estimates.
August 10 - First draft of reference design review graphics/tables (drafts
for proposal) complete.
August 15 - DM only review of reference design graphics/tables
August 22 - LSST leadership review of reference design graphics/tables
August 24 - Freeze reference design and estimates for proposal preparation.

Thanks!

Jeff