Thanks for the response! I was thinking in more of a contingency mode for having one line or transformer for loss of another transformer.
Patrick Dolan, MBA 414.221.4502 From: [email protected] [mailto:[email protected]] On Behalf Of Fred Kanjelesa Sent: Monday, January 13, 2014 7:57 AM To: MATPOWER discussion forum Subject: Re: Transmission Constraints Hi Patrick, If i understand your question well, i think you can do that by defining the power limits for each transmission line in the network. I'm also aware that you can enforce reactive power limits in your network by the following commands >> mpopt=mpoption('ENFORCE_Q_LIMS',1); >> runopf(case.......); i don't know tho if this is possible in the case of real power. Kind regards On 13 January 2014 14:56, Dolan.Patrick <[email protected]<mailto:[email protected]>> wrote: Dear Matpower users, Does anybody know if I can create transmission constraints to be monitored? Thank you, Patrick Dolan , MBA Wisconsin Electric Power Co. d/b/a We Energies mailto: [email protected]<mailto:[email protected]> -- Fred Kanjelesa. NCC-Trading/ZESCO Zambia/Lusaka. Mobile: +260967/955-880912 Extension: 5124 "I can do all things through Christ who strengthens me." Philippians 4:13