Hi Dr Zimmerman and Matpower Community,

I am trying implement an OPF where the real power dispatch is
pre-determined (as in the case of an energy market where the Q
schedules are managed separately by the transmission operator).

Is it possible to implement it in Matpower? My idea is to add "slack"
variables in the nodal energy equations

Pgi - ∆Pgi + Pb1i - Pb2i - Pdi = ΣViVjYij(cos(θij + δi -δj)

Pgi  - fixed/predetermined real power generated at node i
∆Pgi - real power 're-scheduling' due to the reactive power dispatch
Pb1i - upward balancing service at node i
Pb2i - downward balancing service at node i

Pb1i and Pb2 will have non-zero values when ∆Pgi is nonzero, prompting
other generators to compensate the real power 're-scheduling' when
needed.

This is the formulation in the dissertation of Dr.  El-Samahy, and I
am wondering if this can be implemented in matpower.

Any ideas would greatly be appreciated. Thank you very much.

-- 
2 Cor 12:9
Each time he said, "My grace is all you need. My power works best in
weakness." So now I am glad to boast about my weakness, so that the
power of Christ can work through me.


Reply via email to