Dear Sir/s,
I have gone through core load flow programs of MatPower such as gausspf.m and newtonpf.m. But, in these methods, I could not found any provision of switching the PV bus to PQ bus whenever the Q limits of PV bus not met in the duration of iterations. Please let me know your insights into it. -- with Regards ---------------------------------------------------- Gelli Ravikumar Research Scholar (Ph.D), Field Computations Lab, Dept. of Electrical Engineering, IIT Bombay, Powai, Mumbai 400076 Ph: 022-2576 4424, 089 765 983 96 Gandhian Young Technological Innovation Award - 2013 POSOCO Power System Award: PPSA - 2013 IITB PhD Executive Member - 2013-14 IITB SARC Core Technical Member - 2014-15