Without more details of how you are converting your fixed loads to 
dispatchable, I have no way to guess where the 15MW block you are referring to 
comes from. It is certainly not a restriction by MATPOWER.

   Ray


On Sep 18, 2014, at 7:18 AM, nilesh patel <[email protected]> wrote:

> Hello sir,
> i have to use fixed load as dispatchable load to reschedule demand for 
> overload alleviation.
> 
> My question is that after running acopf, i am getting in result each  
> dispatchable load converted to fixed  generation block of 15 MW only. Can 
> this block of 15 MW changed to different value?
> 
> Thanks.
> 
> Nilesh Patel