Another possible approach is to use an OPF and shift the prices down for the 
sending group of generators and up for the receiving group.

    Ray


> On Apr 1, 2015, at 8:02 AM, Abhyankar, Shrirang G. <[email protected]> 
> wrote:
> 
> Although Matpower does not have a function for ATC, it has all the required 
> building blocks for doing the calculations You can take a look at the 
> continuation power flow feature in the MatPower manual as a starting point.
> 
> Shri
> 
> On Apr 1, 2015, at 5:07 AM, "Aruna Dharmala" <[email protected] 
> <mailto:[email protected]>> wrote:
> 
>> Respected sir,
>>                        can we do available transfer capability calculation 
>> using matpower it is possible..?
>>                          if it possible in this software how the interfacing 
>> between two areas of available transfer capability takes place for group of 
>> buses