Another possible approach is to use an OPF and shift the prices down for the
sending group of generators and up for the receiving group.
Ray
> On Apr 1, 2015, at 8:02 AM, Abhyankar, Shrirang G. <[email protected]>
> wrote:
>
> Although Matpower does not have a function for ATC, it has all the required
> building blocks for doing the calculations You can take a look at the
> continuation power flow feature in the MatPower manual as a starting point.
>
> Shri
>
> On Apr 1, 2015, at 5:07 AM, "Aruna Dharmala" <[email protected]
> <mailto:[email protected]>> wrote:
>
>> Respected sir,
>> can we do available transfer capability calculation
>> using matpower it is possible..?
>> if it possible in this software how the interfacing
>> between two areas of available transfer capability takes place for group of
>> buses