The reserve requirement is a lower bound on the sum of reserves for the zone. 
If you make it an upper bound then there is no incentive to provide any 
reserves at all and zero reserves will always be the optimal solution.

   Ray


On Jan 15, 2020, at 3:09 AM, Yang 
<[email protected]<mailto:[email protected]>> wrote:

Dear Ray,
Thanks for your reply!  Flexible, I mean, you see in run_w_res(), there is a 
fixed value requirement for each reserve, and I don't want this fixed value, 
can it just be a limit, so the reserve result will change when the load change.
For example, we give the 10MW for zone 1 with gen1 and gen2, so the sum reserve 
of gen1 and gen2 is 10MW. But I want this 10MW to be a limit, and maybe the sum 
reserve of gen1 and gen2 less than 10MW, it is not necessary for their sum to 
be 10MW.
May I have ways to implement it?

Thanks a lot.
Yang.





At 2020-01-15 06:49:54, "Ray Daniel Zimmerman" 
<[email protected]<mailto:[email protected]>> wrote:

I’m not sure what you mean by flexible. Do you mean price-dependent? The 
current implementation does not include that.

   Ray


On Jan 8, 2020, at 1:11 AM, Yang 
<[email protected]<mailto:[email protected]>> wrote:

Dear Ray,
In runopf_w_res() , the zonal requirement is fixed, but I want it to be 
flexible, how can I do this ?
Thanks.






At 2020-01-03 01:36:43, "Ray Daniel Zimmerman" 
<[email protected]<mailto:[email protected]>> wrote:

Hi Yang,

It’s not clear whether you simply want to use the fixed reserves extension (see 
Section 7.6.1 in the MATPOWER User’s 
Manual<https://matpower.org/docs/MATPOWER-manual-7.0.pdf>) or you want to 
implement your own OPF extension. In the first case you can simply use 
runopf_w_res(). In the second, please see Chapter 7 and the code for the 
various extensions described in Section 7.6.

   Ray


On Dec 25, 2019, at 8:11 PM, Yang 
<[email protected]<mailto:[email protected]>> wrote:

Dear sir,
I want to do the extensible OPF, and I read paper MATPOWER’s Extensible Optimal 
Power Flow Architecture.
The objective function is min f(x)+fu(x,z),and fu=sum(ci*ri), following the 
code:
Ar = [I I];
om = add_vars(om, 'R', ng, [], Rmin, Rmax);
om = add_constraints(om, 'Pg_plus_R', Ar, [], Pmax, {'Pg', 'R'});
om = add_constraints(om, 'Rreq', Az, Rreq, [], {'R'});
om = add_costs(om, 'Rcost', struct('N',I,'Cw',Rcost), {'R'});

I add these into .m file, as for add_vars if I should change [], Rmin, Rmax 
into data I need, and do the same with other codes.
I don't know if it's right.
Best regards.

Yang.