Colin,

There's probably an easier way, but if you decalare a variable, such as
#LastFeed, then #EVAL(#LastFeed=#FEED) at the end of the @FXD or @OP_
section,
you could use #IF(#FEED<>#LastFeed)< F#FEED> within the @FXD or @OP_ section
to control output of the #FEED variable.

Dave

-----Original Message-----
From: [EMAIL PROTECTED]
[mailto:[EMAIL PROTECTED]]On Behalf Of Colin Williams
Sent: Monday, April 24, 2000 2:38 PM
To: Smartcam Forum
Subject: [mfg-smartcam] canned cycle


pmill v11.0:

When using canned cycles on different faces you would normally cancel (g80)
then go onto the next face. Every time you call up the same canned cycle for
different faces the feedrate is also called up. Is there a way just to call
up the feedrate just at the first canned cycle? This way the operator just
has to change the first feedrate.

Thank You

Colin Williams
Wabtec Corporation



======================================================================
To find out more about this mailing list including how to unsubscribe,
send the message "info mfg-smartcam" to [EMAIL PROTECTED]
======================================================================

======================================================================
To find out more about this mailing list including how to unsubscribe,
send the message "info mfg-smartcam" to [EMAIL PROTECTED]
======================================================================

Reply via email to